The East Anglia TWO Offshore Wind Farm Order 2022

Development consent etc. granted by the OrderE+W+S

3.—(1) Subject to the provisions of this Order and to the requirements the undertaker is granted—

(a)development consent for the authorised development; and

(b)consent for the ancillary works,

to be carried out within the Order limits.

(2) Each of the scheduled works must be constructed and maintained within the limits of deviation for that work.

Commencement Information

I1Art. 3 in force at 22.4.2022, see art. 1(2)