The East Anglia TWO Offshore Wind Farm Order 2022

Status:

This is the original version (as it was originally made).

PART 8Protection of NNB Generation Company (SZC) Limited

Application

1.  For the protection of SZC Co. the following provisions of this Schedule have effect unless otherwise agreed in writing between the undertaker and SZC Co.

Interpretation

2.  In this Part of this Schedule—

“SZC Co.” means NNB Generation Company (SZC) Limited (company number 09284825).

Interaction at Sizewell Gap

3.  The undertaker shall consult with SZC Co. in the preparation of the Sizewell Gap construction method statement, to the extent that it relates to Work No. 15, prior to submission of the Sizewell Gap construction method statement to the relevant planning authority for approval in accordance with requirement 22.

Interaction at Snape Road

4.  The undertaker shall consult with SZC Co. in the formulation of the proposed method of working and timing of execution of works within the area of Work No. 35, prior to Work No. 35 commencing.

Interaction at Friday Street

5.  The undertaker shall consult with SZC Co. in the formulation of the proposed method of working and timing of execution of works within the area of Work No. 36, prior to Work No.36 commencing.

Sizewell C proposed intake infrastructure

6.—(1) Save for urgent reasons of vessel safety and subject to sub-paragraph (2), the undertaker shall not carry out any of the authorised project (including the placement temporary or otherwise of anchors or moorings) within the area labelled “Overlap of Sizewell C Order limits with East Anglia TWO Order limits” and hatched purple on the Sizewell C Order Limits Interaction – Offshore Plan (Drawing No. EA2-DEV-DRG-IBR-001284) without having first submitted to and secured approval from SZC Co. details of the proposed method of working within these areas (such approval not to be unreasonably withheld or delayed) and thereafter the undertaker shall implement the authorised project in full accordance with such approved details.

(2) Nothing in this paragraph shall prevent the passage of vessels within the area specified in sub-paragraph (1) prior to the construction of any works within that location by SZC Co. at any time.

Acquisition of land

7.  Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not, to the extent that the exercise of such powers relates to the carrying out of Work Nos. 15, 35 or 36, acquire any land interest or rights or impose restrictive covenants over land belonging to SZC Co. and may not override or extinguish any easement and/or other rights or interests of SZC Co. otherwise than by agreement.

Arbitration

8.  Any difference or dispute arising between SZC Co. and the undertaker must, unless otherwise agreed in writing between SZC Co. and the undertaker, be determined by arbitration in accordance with article 37 (arbitration) of the Order.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources