The Little Crow Solar Park Order 2022

Changes over time for: Section 2

 Help about opening options

Alternative versions:

Status:

Point in time view as at 27/04/2022.

Changes to legislation:

There are currently no known outstanding effects for the The Little Crow Solar Park Order 2022, Section 2. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

InterpretationE+W+S

2.—(1) In this Order except where provided otherwise—

the 1961 Act” means the Land Compensation Act 1961(1);

the 1980 Act” means the Highways Act 1980(2);

the 1989 Act” means the Electricity Act 1989(3);

the 1990 Act” means the Town and Country Planning Act 1990(4);

the 1991 Act” means the New Roads and Street Works Act 1991(5);

the 2008 Act” means the Planning Act 2008(6);

address” includes any number or address for the purposes of electronic transmission;

apparatus” has the same meaning as in section 105(1) of the 1991 Act;

archaeological management plan” means the document certified as the archaeological management plan for the purposes of this Order under article 14 (certification of plans, etc);

authorised development” means the development and associated development described in Schedule 1 (authorised development) which is development within the meaning of section 32 of the 2008 Act;

battery energy storage” means equipment used for the storage of electrical energy by battery;

building” includes any structure or erection or any part of a building, structure or erection;

cable circuit” means an electrical conductor necessary to transmit electricity between two points within the authorised development and may include one or more auxiliary cables for the purpose of gathering monitoring data;

CCTV” means a closed circuit television security system;

commence” means to carry out any material operation (as defined in section 155 of the 2008 Act) forming part of the authorised development other than site preparation works, and “commencement” and “commenced” must be construed accordingly;

construction compound” means a compound including central offices, welfare facilities, accommodation facilities, storage and parking for construction of the authorised development and other associated facilities;

electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

environmental statement” means the document certified by the Secretary of State as the environmental statement for the purposes of this Order under article 14 (certification of plans, etc);

hedgerow plan” means the plan identifying hedgerows and important hedgerows and certified by the Secretary of State for the purposes of this Order under article 14 (certification of plans, etc);

highway” and “highway authority” have the same meaning as in the 1980 Act(7);

inverter” means electrical equipment required to convert direct current power generated by the solar panels to alternating current power;

land plan including Order limits” means the plan certified by the Secretary of State as the land plan including Order limits for the purposes of this Order under article 14 (certification of plans, etc);

LEMP” means the landscape and ecological plan approved pursuant to requirement 10;

local planning authority” means the planning authority for North Lincolnshire;

maintain” includes inspect, upkeep, repair, adjust, alter, remove, reconstruct and replace in relation to the authorised development, provided such works do not give rise to any materially new or materially different environmental effects to those identified in the environmental statement; and any derivative of “maintain” must be construed accordingly;

mounting structure” means a frame or rack with posts made of galvanised steel or other material pushed into the ground to support the solar panels;

Order limits” means the limits shown on the land plan including Order limits within which the authorised development may be carried out;

outline BSMP” means the plan certified by the Secretary of State as the battery safety management plan for the purposes of this Order under article 14(certification of plans, etc);

outline CEMPs” means the outline construction environmental management plan and the outline construction environmental management plan for biodiversity certified by the Secretary of State as the outline CEMPs for the purposes of this Order in accordance with article 14 (certification of plans, etc);

outline CTMP” means the document certified by the Secretary of State as the outline construction traffic management plan for the purposes of the Order in accordance with article 14 (certification of plans, etc);

outline decommissioning strategy” means the document certified as the outline decommissioning strategy by the Secretary of State for the purposes of this Order under article 14 (certification of plans, etc);

outline LEMP” means the document certified by the Secretary of State as the outline landscape and ecological management plan for the purposes of this Order in accordance with article 14 (certification of plans, etc);

outline soil management plan” means the document certified by the Secretary of State as the outline soil management plan for the purposes of this Order in accordance with article 14 (certification of plans, etc);

proposed temporary diversion of public footpath 214 plan” means the plan showing footpath 214 and its proposed temporary diversion certified by the Secretary of State for the purposes of this Order under article 14 (certification of plans, etc);

requirement” means those matters set out in Part 1 of Schedule 2 (requirements) and a reference to a numbered requirement is a reference to the requirement set out in the paragraph of that Part of that Schedule with the same number;

site preparation works” means operations consisting of pre–construction surveys and/or monitoring, site clearance, demolition work, archaeological investigations, environmental surveys, investigations for the purpose of assessing ground conditions, remedial work in respect of adverse ground conditions, diversion and laying of services, erection of any temporary means of enclosure, the temporary display of site notices or advertisements;

solar panel” means a solar photovoltaic panel designed to convert solar irradiance to direct current electrical energy fitted to a mounting structure;

street” means a street within the meaning of section 48 of the 1991 Act, together with land on the verge of a street or between two carriageways, and includes part of a street;

street authority” in relation to a street, has the same meaning as in Part 3 of the 1991 Act(8)

substation” means a compound containing electrical equipment required to switch, transform, convert electricity and provide reactive power compensation with welfare facilities, means of access and other associated facilities;

transformer” means a structure containing electrical switch gear serving to transform electricity generated by the solar panels and imported and exported by the batteries to a higher voltage;

undertaker” means INRG Solar (Little Crow) Limited company number 11136483, whose registered office is at 93 Leigh Road, Eastleigh, Hants, England SO50 9DQ;

watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain;

work” means a work set out in Schedule 1 (authorised development); and

works plan” means the plan certified by the Secretary of State as the works plan for the purposes of this Order in accordance with article 14 (certification of plans, etc).

(2) All distances, directions, capacities and lengths referred to in this Order are approximate and distances between points on a work are taken to be measured along that work.

(3) Any reference in this Order to a work identified by the number of the work is to be construed as a reference to the work of that number authorised by this Order.

(4) In this Order “includes” must be construed without limitation unless the contrary intention appears.

(5) References in this Order to any statutory body include that body’s successor bodies as from time to time have jurisdiction in relation to the authorised development.

Commencement Information

I1Art. 2 in force at 27.4.2022, see art. 1

(7)

“highway” is defined in section 328 (1) for “highway authority” see Section 1.

(8)

“street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c. 7).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources