SCHEDULE 2REQUIREMENTS
PART 1REQUIREMENTS
Interpretation
1.
In this Schedule—
“BSMP” means battery safety management plan;
“CEMPs” means construction environmental management plan and construction environmental management plan for biodiversity;
“contaminated land” has the same meaning as that given in section 78A of the Environmental Protection Act 1990;
“CTMP” means construction traffic management plan;
“first export date” means the date on which the generating station first exports electricity to the Northern Powergrid network on a commercial basis;
“landowner” means the freehold owner of the land within the Order limits on which the relevant part of Work No. 5 is constructed;
“phase” means a defined section or part of the authorised development, the extent of which is shown in a scheme submitted to and approved by the local planning authority under requirement 5 (phases of authorised development); and
“substation operator” means the operator of the substation from time to time constructed as part of Work No. 4.”