SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Interpretation

1.

In this Schedule—

BSMP” means battery safety management plan;

business days” means a day other than Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 of the Banking and Financial Dealings Act 197123;

CEMPs” means construction environmental management plan and construction environmental management plan for biodiversity;

contaminated land” has the same meaning as that given in section 78A of the Environmental Protection Act 1990;

CTMP” means construction traffic management plan;

first export date” means the date on which the generating station first exports electricity to the Northern Powergrid network on a commercial basis;

landowner” means the freehold owner of the land within the Order limits on which the relevant part of Work No. 5 is constructed;

phase” means a defined section or part of the authorised development, the extent of which is shown in a scheme submitted to and approved by the local planning authority under requirement 5 (phases of authorised development); and

substation operator” means the operator of the substation from time to time constructed as part of Work No. 4.”