The Little Crow Solar Park Order 2022

Protected SpeciesE+W+S

14.—(1) No work, including site preparation works, shall be commenced in any phase of the authorised development until final pre-construction survey work has been carried out for that phase to establish whether a protected species is present on any of the land affected, or likely to be affected, by the authorised development or in any of the trees to be lopped or felled as part of that phase.

(2) Where a protected species is shown to be present, the authorised development must not be commenced within that phase until a scheme of protection and mitigation measures has been submitted to and approved by the local planning authority in consultation with Natural England.

(3) The authorised development must be carried out in accordance with any scheme approved under sub-paragraph (2).

(4) In this requirement, “protected species” refers to any species defined as a European Protected Species in regulations 42 (European protected species of animals) and 46 (European protected species of plants) of the Conservation of Habitats and Species Regulations 2017(1) or any species to which Part I (wildlife) and Schedule 5 (animals which are protected) of the Wildlife and Countryside Act 1981(2) applies.

Commencement Information

I1Sch. 2 para. 14 in force at 27.4.2022, see art. 1