Print Options
PrintThe Whole
Instrument
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Paragraph 20


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 27/04/2022.
Changes to legislation:
There are currently no known outstanding effects for the The Little Crow Solar Park Order 2022, Paragraph 20.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Further information regarding requirementsE+W+S
20.—(1) In relation to any application referred to in paragraph 19, the local planning authority may request such further information from the undertaker as it considers necessary to enable it to consider the application.
(2) If the local planning authority considers that further information is necessary and the requirement concerned contained in Part 1 of this Schedule does not specify that consultation with a consultee is required, the local planning authority must, within fourteen days of receipt of the application, notify the undertaker in writing specifying the further information required.
(3) If the requirement concerned contained in Part 1 of this Schedule specifies that consultation with a consultee is required, the local planning authority must issue the application to the consultee within seven days of receipt of the application, and notify the undertaker in writing specifying any further information requested by the consultee within seven days of receipt of such a request.
(4) If the local planning authority does not give the notification within the period specified in sub-paragraph (2) or (3) it (and the consultee, as the case may be) is deemed to have sufficient information to consider the application and is not entitled to request further information without the prior agreement of the undertaker.