PART 6OPERATIONS

Felling or lopping of trees and removal of hedgerows

34.—(1) The undertaker may fell or lop any tree or shrub within or overhanging land within the Order limits, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b)from constituting a danger to persons using the authorised development.

(2) In carrying out any activity authorised by paragraphs (1) or (4), the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.

(3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined as if it were a dispute under Part 1 of the 1961 Act.

(4) The undertaker may, for the purposes of carrying out the authorised development but subject to paragraph (2), remove any hedgerow described in Part 1 (trees) of Schedule 8 (hedgerows and trees).

(5) The undertaker may, for the purposes of carrying out the authorised development but subject to paragraph (2), remove any hedgerow which is not described in Part 1 of Schedule 8 with the prior consent of the local authority.

(6) In this article “hedgerow” has the same meaning as in the Hedgerow Regulations 1997(1) and includes important hedgerows.

Trees subject to tree preservation orders

35.—(1) The undertaker may fell or lop any tree described in Part 2 (trees subject to tree preservation orders) of Schedule 8 or cut back its roots or undertake such other works if it reasonably believes it to be necessary in order to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project; or

(b)from constituting a danger to passengers or other persons using the authorised project.

(2) In carrying out any activity authorised by paragraph (1)—

(a)the undertaker shall do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity; and

(b)the duty contained in section 206(1) (replacement of trees) of the 1990 Act is not to apply.

(3) The authority given by paragraph (1) shall constitute a deemed consent under the relevant tree preservation order.

(4) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined as if it were a dispute under Part 1 of the 1961 Act.

Back to top