The M54 to M6 Link Road Development Consent Order 2022

Signage to Saredon Filling Station

11.  No part of the authorised development constituting Work No. 36 is to commence unless the undertaker has first consulted with the local highway authority and the proprietors of the Saredon Filling Station regarding a scheme for the signage regarding that Work. The written details regarding Work No. 36 must be submitted and approved in writing by the Secretary of State and must include provision of directional signage to the Saredon Filling Station and the approved signage must be installed in full in accordance with the approved details before the new M6 Junction 11 circulatory carriageway is open for traffic.