There are currently no known outstanding effects for the The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022, PART 2.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Commencement Information
I1Sch. 3 Pt. 2 in force at 2.6.2022, see art. 1
(1) Highway | (2) Extent |
---|---|
M25 junction 10, circulatory carriageway | For the entire extent of the altered M25 junction 10 circulatory carriageway, as shown between points 5/6 and 5/7 on Sheet 5 of the streets, rights of way and access plans, comprising 725 metres. |
A3 northbound | Improved A3 northbound carriageway, as shown between point 1/1 on Sheet 1 and point 8/12 on Sheet 8 of the streets, rights of way and access plans, comprising 5,325 metres. |
A3 northbound on-slip at the A3 Ockham Park junction | Improved slip road, as shown between points 1/15 and 1/16 on Sheet 1 of the streets, rights of way and access plans, comprising 90 metres and between point 1/16 on Sheet 1 and point 2/2 on Sheet 2 of the streets, rights of way and access plans, comprising 650 metres. |
A3 northbound off-slip at M25 junction 10 | Improved slip road, as shown between point 4/11 on Sheet 4 and point 5/8 on Sheet 5 of the streets, rights of way and access plans, comprising 315 metres. |
A3 northbound on-slip at M25 junction 10 | Improved slip road, as shown between point 5/14 on Sheet 5 and point 6/2 on Sheet 6 of the streets, rights of way and access plans, comprising 465 metres. |
A3 northbound off-slip at the A3 Painshill junction | Improved slip road, as shown between point 7/3 on Sheet 7 and point 8/5 on Sheet 8 of the streets, rights of way and access plans, comprising 685 metres. |
A3 northbound on-slip at the A3 Painshill junction | Improved slip road, as shown between points 8/10 and 8/11 on Sheet 8 of the streets, rights of way and access plans, comprising 120 metres. |
A3 southbound | Improved A3 southbound carriageway, as shown between point 8/13 on Sheet 8 and point 1/2 on Sheet 1 of the streets, rights of way and access plans, comprising 5,530 metres. |
A3 southbound off-slip at the A3 Painshill junction | Improved slip road, as shown between points 8/14 and 8/15 on Sheet 8 of the streets, rights of way and access plans, comprising 245 metres. |
A3 southbound on-slip at the A3 Painshill junction | Improved slip road, as shown between point 8/19 on Sheet 8 and point 7/2 on Sheet 7 of the streets, rights of way and access plans, comprising 785 metres. |
A3 southbound off-slip at M25 junction 10 | Altered slip road, as shown between point 6/1 on Sheet 6 and point 5/19 on Sheet 5 of the streets, rights of way and access plans, comprising 305 metres. |
A3 southbound on-slip at M25 junction 10 | Altered slip road, as shown between point 5/5 on Sheet 5 and point 4/1 on Sheet 4 of the streets, rights of way and access plans, comprising 870 metres. |
A3 southbound off-slip at the A3 Ockham Park junction | Improved slip road, as shown between point 2/1 on Sheet 2 and point 1/22 on Sheet 1 of the streets, rights of way and access plans, comprising 380 metres. |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: