Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Commencement Information
I1Sch. 3 Pt. 8 in force at 2.6.2022, see art. 1
(1) Public right of way | (2) Extent |
---|---|
Cycle track | 65 metres of cycle track connecting the A3 northbound with the B2115 Portsmouth Road, as shown between points 1/3 and 1/4 on Sheet 1 of the streets, rights of way and access plans. |
Footway | 15 metres of footway in verge of the B2115 Portsmouth Road, as shown between points 1/5 and 1/33 on Sheet 1 of the streets, rights of way and access plans. |
Non-segregated footway/cycle track | 310 metres of non-segregated footway/cycle track in verge of the B2215 Portsmouth Road and B2039 Ockham Park junction, as shown between points 1/5 and 1/8 on Sheet 1 of the streets, rights of way and access plans, with a signal controlled toucan crossing facility at point 1/e as shown on Sheet 1. |
Non-segregated footway/cycle track | 25 metres of non-segregated footway/cycle track at the tie-in between the B2115 Portsmouth Road and the A3 Ockham Park junction circulatory carriageway, as shown between points 1/9 and 1/10 on Sheet 1 of the streets, rights of way and access plans, with a signal controlled toucan crossing facility located at point 1/a as shown on Sheet 1. |
Non-segregated footway/cycle track | 370 metres of non-segregated footway/cycle track in verge of the B2215 Portsmouth Road and B2039 Ockham Park junction, as shown between points 1/11 and 1/12 on Sheet 1 of the streets, rights of way and access plans, with signal controlled toucan crossing facilities located at points 1/b, 1/c and 1/d as shown on Sheet 1. |
Footway | 70 metres of footway in the verge of the A3 Ockham Park junction and the A3 northbound on-slip, as shown between points 1/13 and 1/14 on Sheet 1 of the streets, rights of way and access plans. |
Bridleway | 50 metres of bridleway in verge of the A3 Ockham Park junction and the B2039 Ockham Road North, as shown between points 1/12 and 1/26 on Sheet 1 of the streets, rights of way and access plans. |
Footway | 75 metres of footway in verge of the A3 southbound off-slip at the Ockham Park junction, as shown between points 1/23 and 1/24 on Sheet 1 of the streets, rights of way and access plans. |
Bridleway | 1,340 metres of bridleway in verge, as shown between point 1/12 on Sheet 1 and point 20/5 on Sheet 20 of the streets, rights of way and access plans. |
Footpath | 105 metres of footpath, as shown between points 1/29 and 1/31 on Sheet 1 of the streets, rights of way and access plans. |
Bridleway | 320 metres of bridleway, as shown between point 2/3 on Sheet 2 and point 23/1 on Sheet 23 of the streets, rights of way and access plans, to include reclassification of 175 metres of unclassified road (Elm Lane) to bridleway, as shown between point 2/11 on Sheet 2 and point 23/1 on Sheet 23 of the streets, rights of way and access plans. |
Footpath | 130 metres of footpath, as shown between points 2/4 and 2/7 on Sheet 2 of the streets, rights of way and access plans, comprising the reclassification of 130 metres of an existing unclassified road (Elm Lane) as footpath. |
Footpath | 30 metres of footpath, as shown between points 2/5 and 2/7 on Sheet 2 of the streets, rights of way and access plans. |
Footpath | 5,855 metres of footpath, as shown between point 2/7 on Sheet 2 and point 3/2 on Sheet 3 of the streets, rights of way and access plans. |
Footpath | 105 metres of footpath, as shown between point 2/10 on Sheet 2 and point 3/1 on Sheet 3 of the streets, rights of way and access plans. |
Bridleway | 845 metres of bridleway, as shown between point 4/4 on Sheet 4 and point 12/6 on Sheet 12 of the streets, rights of way and access plans. |
Bridleway | 20 metres of bridleway, as shown between points 4/4 and 4/6, as shown on Sheet 4 of the streets, rights of way and access plans. |
Bridleway | 180 metres of bridleway, as shown between points 4/7 and 4/8 on Sheet 4 of the streets, rights of way and access plans. |
Footpath | 75 metres of footpath, as shown between points 4/8 and 4/9 on Sheet 4 of the streets, rights of way and access plans. |
Bridleway | 1,100 metres of bridleway, as shown between point 5/22 on Sheet 5 and point 14/3 on Sheet 14 of the streets, rights of way and access plans. |
Bridleway | 815 metres of bridleway, as shown between point 5/35 on Sheet 5 and point 13/6 on Sheet 13 of the streets, rights of way and access plans, comprising the reclassification of 775 metres of unclassified road (Pointers Road) to bridleway. |
Footpath | 370 metres of footpath, as shown between point 6/3 on Sheet 6 and point 28/1 on Sheet 28 of the streets, rights of way and access plans. |
Bridleway | 1,300 metres of bridleway, as shown between point 6/5 on Sheet 6 and point 12/1 on Sheet 12 of the streets, rights of way and access plans. |
Bridleway | 860 metres of bridleway, as shown between point 6/6 on Sheet 6 and point 13/5 on Sheet 13 of the streets, rights of way and access plans. |
Bridleway | 4,265 metres of bridleway, as shown between point 7/1 on Sheet 7 and point 20/5 on Sheet 20 of the streets, rights of way and access plans, to include the reclassification of 140 metres of Seven Hills Road from B365 to bridleway. |
Non-segregated footway/cycle track | 140 metres of non-segregated footway/cycle track in the verge of the A3 Painshill junction roundabout, as shown between points 8/24 and 8/26 on Sheet 8 of the streets, rights of way and access plans. |
Non-segregated footway/cycle track | 550 metres of non-segregated footway/cycle track in the verge of the A245 Byfleet Road westbound carriageway westbound carriageway, as shown between point 8/24 on Sheet 8 and point 9/11 on Sheet 9 of the streets, rights of way and access plans. |
Footpath | 175 metres of footpath adjacent to the A3 southbound on-slip at the A3 Painshill junction, as shown between points 8/20 and 8/23 on Sheet 8 of the streets, rights of way and access plans. |
Footway | 12 metres of footway between the new dedicated slip road connecting the A245 Byfleet Road (westbound) with Seven Hills Road (south) and the A245 Byfleet Road/Seven Hills Road junction, as shown between points 9/12 and 9/13 on Sheet 9 of the streets, rights of way and access plans. |
Footway | 130 metres of footway in verge of A245 Byfleet Road (eastbound), as shown between points 9/3 and 9/4 on Sheet 9 of the streets, rights of way and access plans. |
Bridleway | 445 metres of bridleway, as shown between points 11/3 and 11/4 on Sheet 11 of the streets, rights of way and access plans. |
Footpath | 135 metres of footpath, as shown between points 20/1 and 20/2 on Sheet 20 of the streets, rights of way and access plans. |
Byway 525 (Byway Open to All Traffic) improvement | 565 metres of Byway Open to All Traffic, as shown between points 24/1 and 24/2 on Sheet 24 of the streets, rights of way and access plans. |
Footpath | 558 metres of footpath, as shown between points 26/1 and 26/2 on Sheet 26 of the streets, rights of way and access plans. |
Footpath | 12 metres of footpath, as shown between points 26/3 and 26/4 on Sheet 26 of the streets, rights of way and access plans. |
Bridleway | 855 metres of bridleway, as shown between point 27/1 on Sheet 27 and point 28/2 on Sheet 28 of the streets, rights of way and access plans. |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: