The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022

Changes over time for: SCHEDULE 5

 Help about opening options

Alternative versions:

Status:

Point in time view as at 19/01/2023.

Changes to legislation:

There are currently no known outstanding effects for the The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022, SCHEDULE 5. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 25

SCHEDULE 5E+WLAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

Commencement Information

I1Sch. 5 in force at 2.6.2022, see art. 1

(1)

Plot Reference Number shown on Land Plans

(2)

Purpose for which rights over land may be acquired

(3)

Relevant part of the authorised development

Land Plans – Sheet 1
1/18aTo provide, construct, inspect, retain, access, maintain, renew and repair environmental mitigation works on land adjoining Stratford Brook.Work No.54
1/40To construct, retain, inspect, operate, access maintain and repair a diverted gas pipeline and associated equipment.Work No.63(a)
Land Plans – Sheet 2
2/8

For use as a construction access route.

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.34
2/9, 2/10, 2/14

For use as a construction access route.

For use as a maintenance access for the authorised development.

Work No.23(b)

Work No.33(c)

Work No.33(d)

Work No.36

Work No.52(c)

Work No.63(a)

2/12To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment and a filter drain.Work No.63(a)
2/12aTo construct, operate, access and maintain a carrier drain.Work No.52(b)
2/13aTo construct, access and maintain a pre-earthworks ditch.Work No.33
2/14a

For use as a construction access route.

To construct a footpath and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, operate, access and maintain a carrier drain.

For use as a maintenance access for the authorised development.

Work No.33(c)

Work No.52(b)

Work No.63(a)

2/14b

For use as a construction access route.

To construct a footpath and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, operate, access and maintain a carrier drain.

For use as a maintenance access for the authorised development.

Work No.33(c)

Work No.52(b)

Work No.63(a)

2/28a

To construct the realignment of the access to RHS Garden Wisley, to include provision of a new bus stop facility.

To construct, operate, access, and maintain the diversion of electric cables and associated apparatus and equipment.

Work No.33(f)

Work No.62(c)

2/28c

To construct the realignment of the access to RHS Garden Wisley, to include provision of a new bus stop facility.

To construct, operate, access, and maintain the diversion of electric cables and associated apparatus and equipment.

To construct, operate, access, and maintain the diversion of telecommunication cables, media cables and equipment.

Work No.33(f)

Work No.62(c)

Work No.65(c)

2/36

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to a gas pipeline and associated equipment, the width of the new right within the plot not to exceed 6 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.63(a)

Land Plans – Sheet 3
3/3aTo construct and use as a maintenance access for the authorised development.

Work No.1(a)

Work No.1(c)

Work No.64(a)

3/3bTo construct, operate, access and maintain a diversion to a gas pipeline and associated equipment, the width of the new right not to exceed 6 metres.Work No.63(a)
3/3dTo construct and use as a maintenance access in relation to a gantry and utility diversion.

Work No.64(a)

Work No.23(c)

3/9To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(b)
3/13To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(a)
3/16

To construct a footpath and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.36
3/19To construct, inspect, access and maintain a retaining wall and associated planting.Work No.5(c)
3/19aTo undertake, retain, inspect, access, maintain, monitor and renew environmental mitigation and enhancement works.Work No.55
3/25

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new right not to exceed 6 metres.

To construct, operate, access and maintain an extension of an existing culvert.

For use as a maintenance access for the authorised development.

Work No.1(e)

Work No.35

Work No.63(a)

3/26a

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, operate, access and maintain an extension of an existing culvert.

To construct, operate, access and maintain a carrier drain.

For use as a maintenance access for the authorised development.

Work No.1(e)

Work No.35

Work No.52(d)

Work No.63(a)

3/27To construct, operate, access and maintain an extension of an existing culvert.Work No.1(e)
3/31Right of access for the purposes of environmental compensation works.

Work No.57

Work No.58

3/32

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new right not to exceed 6 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.63(a)

3/37

To construct, operate, access and maintain an extension of an existing culvert.

To construct, operate, access and maintain a carrier drain.

To undertake, retain, inspect, access, maintain, a highway fence.

Work No.1(e)

Work No.52(d)

Land Plans – Sheet 4
4/1Right of access for the purposes of environmental compensation works.

Work No.57

Work No.58

4/3c

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new right within the plot not to exceed 6 metres.

To construct, inspect, access and maintain a retaining wall and highway fence.

For use as a maintenance access for the authorised development.

Work No.1(a)

Work No.1(c)

Work No.35

Work No.63(a)

4/3d

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, operate, access and maintain a diversion to existing electric lines, cables, equipment and apparatus.

The width of the new right within the plot not to exceed 6 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.62(d)

Work No.63(a)

4/4, 4/4a, 4/10

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new right within the plot not to exceed 6 metres.

To construct, inspect, access and maintain a retaining wall and highway fence.

For use as a maintenance access for the authorised development.

Work No.35

Work No.63(a)

4/4b

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to existing electric lines, cables, equipment and apparatus, the width of the new right within the plot not to exceed 6 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.62(d)

Work No.63(a)

4/15aTo undertake, retain, inspect, access, maintain, monitor and renew environmental mitigation and enhancement works.Work No.55
4/20

To construct a bridleway and use as a substitute private means of access, and maintenance access.

For use as a maintenance access for the authorised development.

Work No.35

Work No.35(b)

Work No.35(d)

4/21To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(d)
4/22bTo construct and use an access to environmental compensation works.Work No.58(d)
4/23

To construct a bridleway and associated drainage and for use as a substitute private means of access, maintenance access, and for the maintenance of Cockcrow overbridge.

For use as a maintenance access for the authorised development.

Work No.35

Work No.35(b)

Work No.35(d)

4/30

To construct an access and associated drainage and for use as a substitute private means of access.

The width of the new rights within the plot not to exceed 3.5 metres.

Work No.35(c)
4/31, 4/34

To construct a bridleway and use as a maintenance access.

The width of the new rights within the plot not to exceed 3 metres.

For use as a maintenance access for the authorised development.

Work No.35
4/37, 4/38To construct, access and maintain a soakaway.Work No.52(f)
4/41

To construct a bridleway and use as a maintenance access.

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

To construct, access and maintain a soakaway and pre-earthwork ditch.

The width of the new rights within the plot not to exceed 3 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.7

4/43, 4/45a

To construct a bridleway and associated drainage, for use as a substitute private means of access, maintenance access and for the maintenance of Cockcrow overbridge.

The width of the new rights within the plot not to exceed 4.1 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.35(b)

4/43aTo construct, access and maintain a soakaway.Work No.35
4/43b

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new rights within the plot not to exceed 6 metres.

To construct, inspect, access and maintain a highway fence.

Work No.63(a)
4/43c

To construct a bridleway and use as a maintenance access.

The width of the new rights within the plot not to exceed 3 metres.

For use as a maintenance access for the authorised development.

Work No.35
4/43d

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new right within the plot not to exceed 6 metres.

To construct, inspect, access and maintain a highway fence.

For use as a maintenance access for the authorised development.

Work No.35

Work No.63(a)

4/46To construct, maintain and use an access to a drainage attenuation pond.Work No.52(e)
4/47

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, operate, access and maintain a filter drain.

The width of the new rights within the plot not to exceed 6 metres.

Work No.63(a)
4/47a, 4/47b

To construct a bridleway and associated drainage and for use as a substitute private means of access and maintenance access.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment, the width of the new right within the plot not to exceed 6 metres.

For use as a maintenance access for the authorised development.

Work No.35

Work No.63(a)

4/47dTo construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment and filter drain.Work No.63(a)
4/48a, 4/49a

To construct an access and associated drainage and for use as a substitute private means of access.

The width of the new right within the plot not to exceed 3.5 metres.

Work No.35(c)
4/51

To construct a bridleway and associated drainage and for use as a substitute private means of access and maintenance access.

For use as a maintenance access for the authorised development.

Work No.35(c)
4/51a

To construct a bridleway and use as a maintenance access.

The width of the new right within the plot not to exceed 3 metres.

For use as a maintenance access for the authorised development.

Work No.35
4/52, 4/54, 4/67To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(c)
4/61

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, operate, access and maintain a filter drain.

The width of the new right within the plot not to exceed 6 metres.

Work No.63(a)
4/63

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

The width of the new right within the plot not to exceed 6 metres.

Work No.63(a)
4/72

To construct and use an access as a private means of access and maintenance access.

To construct, maintain and use an access to a drainage attenuation pond.

To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.

For use as a construction access route in connection with environmental compensation works.

For use as a maintenance access for the authorised development.

Work No.52(e)

Work No.58(c)

4/73, 4/75, 4/79a, 4/86aTo construct, maintain and use an access to a drainage attenuation pond.Work No.52(e)
4/82

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

The width of the new right within the plot not to exceed 6 metres.

Work No.63(a)
Land Plans – Sheet 5
5/1cTo construct, access and maintain a soakaway.Work No.52(g)
5/1d

To construct a bridleway.

To operate, access and maintain a pre-earthwork ditch, environmental barrier.

Work No.35

Work No.52(g)

Work No.61(d)

5/7

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing watercourse.

For use as a maintenance access for the authorised development.

Work No.35

Work No.53(e)

5/7a

To construct a bridleway and use as a maintenance access.

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

For use as a maintenance access for the authorised development.

Work No.35

Work No.52(i)

Work No.7

5/7cTo construct, access and maintain a soakaway and pre-earthwork ditch.Work No.35
5/7d, 5/7e

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a carrier drain.

To construct, operate, access and maintain a diversion to an existing watercourse.

For use as a maintenance access for the authorised development.

Work No.35

Work No.37

Work No.52(i)

Work No.53(e)

5/8

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.37
5/8a

To construct, operate, access and maintain a diversion to an existing watercourse.

To construct, access and maintain a soakaway.

Work No.53(e)
5/8b

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a diversion to an existing watercourse.

To construct, access and maintain a soakaway.

Work No.53(e)
5/12a, 5/12b

To construct, operate, access and maintain a diversion to existing electric cables and associated apparatus and equipment.

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

Work No.62(g)

Work No.7

5/12c

To construct, operate, inspect, access and maintain an environmental barrier and soakaway.

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

Work No.61(a)

Work No.7

5/13a, 5/13c

To construct, operate, inspect, access and maintain an environmental barrier.

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

Work No.61(a)

Work No.7

5/13b

To construct, operate, access and maintain a diversion to existing electric cables and associated apparatus and equipment.

To construct, operate, inspect, access and maintain an environmental barrier.

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

Work No.61(a)

Work No.62(g)

Work No.7

5/21

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

To construct, access and maintain a pre-earthwork ditch.

To construct, maintain and use an access to a drainage attenuation pond.

Work No.7

Work No.52(h)

5/21a

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

To construct, access and maintain a pre-earthwork ditch.

Work No.7
5/24, 5/24a

To access land to be used for the construction of a temporary slip road in connection with improvements to the M25 junction 10.

To construct, access and maintain a pre-earthwork ditch.

To construct, operate, inspect, access and maintain an environmental barrier.

Work No.7

Work No.61(b)

5/30

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.35
Land Plans – Sheet 6
6/1b, 6/3aTo construct, access and maintain a pre-earthwork ditch.Work No.35
6/2

To construct a bridleway and use as a maintenance access.

To construct, operate, inspect, access and maintain an environmental barrier and filter drain.

For use as a maintenance access for the authorised development.

Work No.35

Work No.35(f)

Work No.61(c)

6/2b

To construct a bridleway and use as a maintenance access.

To construct, operate, inspect, access and maintain an environmental barrier and filter drain.

For use as a maintenance access for the authorised development.

Work No.35

Work No.61(c)

6/4

To construct, operate, inspect, access and maintain an environmental barrier and filter drain.

To construct, operate, access and maintain the diversion of telecommunication cables, media cables and equipment

Work No.61(c)

Work No.65(a)

6/4a, 6/4bTo construct, operate, inspect, access and maintain an environmental barrier and filter drain.Work No.61(c)
6/9, 6/10

To construct a bridleway and use as a maintenance access.

To construct, operate, inspect, access and maintain a retaining wall and filter drain.

For use as a maintenance access for the authorised development.

Work No.35

Work No.39

6/23aTo construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.Work No.63(c)
Land Plans – Sheet 7
7/9, 7/10To construct, operate, access and maintain modifications to access to gas valve compound.

Work No.17(c)

Work No.40

7/15, 7/15a, 7/16To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.Work No.63(c)
7/17

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To undertake, access and maintain tree and shrub planting.

Work No.63(a)
7/23

To construct a bridleway and for use as a private means of access and for use as a maintenance access.

To construct, operate, access and maintain diversions to existing utility connections and associated apparatus and equipment.

For use as a construction access route.

For use as a maintenance access for the authorised development.

Work No.35

Work No.35(k)

Land Plans – Sheet 8
8/5b, 8/5c

To construct, access and maintain the authorised development.

To construct, operate, access and maintain a diversion to electric cables and associated apparatus and equipment.

To access and maintain utility apparatus and equipment.

Work No.18

Work No.18(b)

Work No.40

Work No.65(a)

8/7

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

To construct, inspect, access and maintain a highway fence.

Work No.63(c)
8/11To access, inspect and maintain a retaining wall.Work. No.16
8/12

To construct an access and use as a private means of access.

To construct, operate, access and maintain a diversion to electric cables and associated apparatus and equipment.

To access, inspect and maintain a retaining wall.

Work No.46

Work No.16

Work No.62(o)

8/12aTo access, inspect and maintain a retaining wall.Work. No.16
Land Plans – Sheet 9
9/3

To construct an access and use as a private means of access.

To access, inspect and maintain a retaining wall.

Work No.46

Work No.16

9/13To construct, operate, inspect, access and maintain a carrier drain.Work No.52(l)
Land Plans – Sheet 11
11/2To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.57(a)
11/3To undertake, access and maintain tree and shrub planting.Work No.29
11/4To undertake, retain, inspect, access, maintain, monitor and renew environmental mitigation works.Work No 60
11/6To construct, a bridleway, and filter drain.Work No.49
11/14

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

To construct, operate, access and maintain a soakaway and environmental barrier.

Work No.49

Work No.61(b)

11/14a

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

11/18, 11/18b

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

To construct, inspect, access and maintain a retaining wall.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

11/19

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a soakaway, pre-earthwork ditch and environmental barrier.

The width of the new rights within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

11/19a

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

To construct, inspect, access and maintain a retaining wall.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

11/20To construct, operate, access and maintain a soakaway.Work No.49
11/21

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a pre-earthwork ditch.

For use as a maintenance access for the authorised development.

Work No.49
11/22, 11/22aTo construct, operate, access and maintain a soakaway and environmental barrier.

Work No.49

Work No.61(a)

11/23, 11/24a

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a soakaway and an environmental barrier.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

11/24

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain a soakaway and an environmental barrier.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

11/25

To construct a bridleway and use as a maintenance access.

The width of the new right within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49
11/25aTo construct a bridleway and use as a maintenance access.Work No.49
11/29To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(e)
Land Plans – Sheet 12
12/1cTo construct, operate, access and maintain an environmental barrier.Work No.49
12/4

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

The width of the new right within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

Work No.52(m)

12/4a, 12/5a, 12/5c, 12/5d, 12/5e, 12/7, 12/12, 12/17

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

Work No.52(m)

12/5b

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

The width of the new right within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

Work No.52(m)

12/6To construct, operate, access and maintain an environmental barrier.

Work No.49

Work No.61(a)

Work No.52(m)

12/11

To construct a bridleway and use as a maintenance access and for the maintenance of Clearmount overbridge.

To construct, operate, access and maintain an environmental barrier.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

Work No.52(m)

12/18

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

The width of the new right within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(a)

Work No.52(m)

12/23

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.49

Work No.52(m)

12/25

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

To undertake, access and maintain shrub planting.

For use as a maintenance access for the authorised development.

To construct, operate, access and maintain a diverted gas pipeline and associated equipment.

Work No.49

Work No.61(a)

Work No.52(m)

Work No.63(e)

12/25b

To construct, operate, access and maintain an environmental barrier.

To undertake, access and maintain shrub planting.

To construct, operate, access and maintain a diverted gas pipeline and associated equipment.

Work No.61(a)Work

No.63(e)

12/25cTo construct, operate, access and maintain a soakaway and an environmental barrier.Work No.61(a)
12/27

To construct a bridleway and use as a maintenance access.

To construct, inspect, access and maintain a retaining wall.

For use as a maintenance access for the authorised development.

Work No.49
12/28

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

The width of the new rights within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

12/30

To construct a bridleway and use as a maintenance access.

The width of the new rights within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49
12/31

To construct a bridleway and use as a maintenance access.

To construct, operate, access and maintain an environmental barrier.

The width of the new rights within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

12/34

To construct a bridleway and use as a maintenance access.

To construct, maintain and use an access to a drainage attenuation pond.

To construct, operate, access and maintain an environmental barrier.

The width of the new rights within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

Work No.52(h)

12/34a

To construct, maintain and use an access to a drainage attenuation pond.

To construct, operate, access and maintain an environmental barrier.

To construct, operate, access and maintain a diversion to an existing gas pipeline and associated equipment.

Work No.52(h)

Work No.61(b)

Work No.63(e)

12/34b

To construct, maintain and use an access to a drainage attenuation pond.

To construct, operate, access and maintain an environmental barrier.

The width of the new rights within the plot not to exceed 3.5 metres.

Work No.52(h)

Work No.61(b)

12/34c

To construct a bridleway and use as a maintenance access.

To construct, maintain and use an access to a drainage attenuation pond.

To construct, operate, access and maintain an environmental barrier.

The width of the new rights within the plot not to exceed 3.5 metres.

For use as a maintenance access for the authorised development.

Work No.49

Work No.61(b)

Work No.52(h)

Land Plans – Sheet 13
13/2, 13/2dTo construct, access and maintain a pre-earthworks ditch.

Work No.26

Work No.35(e)

13/2eTo construct, access and maintain a pre-earthworks ditch and environmental barrier.

Work No.26

Work No.35(e)

Work No.61(c)

13/4c, 13/4dTo construct, access and maintain a pre-earthworks ditch and environmental barrier.

Work No.28

Work No.61(d)

13/4e, 13/4f, 13/4gTo construct, access and maintain a pre-earthworks ditch.Work No.28
[F113/9b To construct, access and maintain a pre earthworks ditch and environmental barrier.

Work No.26

Work No.35(e)

Work No.61(c)

13/9cTo construct, access and maintain a filter drain and environmental barrier.

Work No.26

Work No.35(e)

Work No.61(c)]

13/10, 13/11, 13/11a

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.37

Work No.51(i)

13/14, 13/15To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(d)
Land Plans – Sheet 20
20/2, 20/3, 20/4To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(f)
Land Plans – Sheet 21
21/1Right of access for the purposes of environmental compensation works.Work No.58(g)
21/1aRight of access for the purposes of environmental compensation works.

Work No.57

Work No.58

21/2To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(g)
Land Plans – Sheet 23
23/1

To construct a bridleway and use as a maintenance access.

For use as a maintenance access for the authorised development.

Work No.34
Land Plans – Sheet 25
25/1To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.58(h)
Land Plans – Sheet 26
26/1To undertake, retain, inspect, access, maintain, monitor and renew environmental compensation works.Work No.57(b)
26/2

Right of access for the purposes of environmental compensation works.

The width of the new rights within the plot not to exceed 3.5 metres.

Work No.57(b)

Back to top

Options/Help

Print Options

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item