Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
21.—(1) The Authority may revoke a boiler upgrade voucher—
(a)where it is no longer satisfied that the conditions in regulation 14(2) are met in relation to the boiler upgrade voucher,
(b)where it is no longer satisfied that any information required by a notice given under regulation 14(4) in relation to the boiler upgrade voucher is accurate,
(c)where it is satisfied that the installer to whom it has issued the boiler upgrade voucher—
(i)has failed or is failing to comply with an installer obligation, or
(ii)has been issued the voucher as a result of the provision of information which was incorrect in a material particular,
(d)where it is satisfied that—
(i)the person who is specified in the boiler upgrade voucher as the installer is not an installer,
(ii)the property specified in the boiler upgrade voucher is not an eligible property F1... [F2, or]
F3(iii). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(iv)the plant specified in the boiler upgrade voucher is not eligible, or not eligible in relation to the property specified in the voucher, or
(e)at the request of the installer.
(2) Where the Authority is satisfied as set out in paragraph (1)(c) or (d)(i), it may also revoke all other boiler upgrade vouchers issued to the installer.
(3) Within 14 days of a decision to revoke the boiler upgrade voucher under paragraph (1), the Authority must send a notice to the installer specifying—
(a)where paragraph (1)(a) or (b) applies—
(i)the respect in which the Authority is satisfied that the condition is no longer met, or the information is no longer accurate, and
(ii)where applicable, the steps that the installer must take to satisfy the Authority that the condition is met or the information is accurate,
(b)where paragraph (1)(c)(i) applies—
(i)the respect in which the Authority is satisfied that the installer has failed or is failing to comply with the installer obligation, and
(ii)where applicable, the steps that the installer must take to satisfy the Authority that it is complying with the installer obligation,
(c)where paragraph (1)(c)(ii) applies—
(i)details of the respect in which the information was incorrect, and
(ii)where applicable, the steps that the installer must take to satisfy the Authority that, notwithstanding the provision of incorrect information, the boiler upgrade voucher should not be revoked,
(d)where paragraph (1)(c) or (d)(i) applies, details of any other boiler upgrade vouchers issued to the installer that the Authority has decided to revoke under paragraph (2),
(e)where paragraph (1)(d) applies, details of the respect in which the Authority is satisfied as to the matters described in paragraph (1)(d)(i), (ii), (iii) or (iv) (as applicable),
(f)where applicable, any further information the installer must provide to the Authority,
(g)the date by which the steps referred to in sub-paragraph (a)(ii), (b)(ii) or (c)(ii) must be completed, or the information mentioned in sub-paragraph (f) must be provided, which must be within 14 days beginning with the date the notice is issued,
(h)the consequences of the installer failing to take the steps referred to in sub-paragraph (a)(ii), (b)(ii) or (c)(ii), or to provide the information mentioned in sub-paragraph (f), by the date specified, and
(i)where paragraph (1)(a), (b), (c) or (d) applies, details of the installer’s right of review under regulation 25.
(4) The Authority may extend the time specified in the notice in accordance with paragraph (3)(g) where it is satisfied that it is reasonable to do so.
(5) Where the Authority is satisfied that the installer has taken the steps specified in the notice in accordance with sub-paragraph (a)(ii), (b)(ii) or (c)(ii) or provided the information specified in the notice in accordance with sub-paragraph (f), as applicable, within the time specified, it must notify that installer that the boiler upgrade voucher will not be revoked in accordance with this regulation.
(6) Where the Authority revokes a boiler upgrade voucher in accordance with this regulation, regulation 16(8) or 20(5) it—
(a)must update the register, maintained under regulation 28, accordingly, and
(b)may refuse any subsequent grant application by that installer or by a connected person, except where paragraph (1)(e) applies (installer request to revoke).
Textual Amendments
F1Words in reg. 21(1)(d)(ii) omitted (8.5.2024) by virtue of The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 19(a) (with reg. 25)
F2Word in reg. 21(1)(d)(ii) inserted (8.5.2024) by The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 19(b) (with reg. 25)
F3Reg. 21(1)(d)(iii) omitted (8.5.2024) by virtue of The Boiler Upgrade Scheme (England and Wales) (Amendment) Regulations 2024 (S.I. 2024/524), regs. 1(2), 19(c) (with reg. 25)
Commencement Information
I1Reg. 21 in force at 23.5.2022, see reg. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: