The Boiler Upgrade Scheme (England and Wales) Regulations 2022

Regulation 16(3)(a)

SCHEDULE 3E+WInformation required for redemption application

This schedule has no associated Explanatory Memorandum

1.  This Schedule specifies the information that must be provided in support of a redemption application.E+W

Commencement Information

I1Sch. 3 para. 1 in force at 23.5.2022, see reg. 1(1)

2.  The information is—E+W

(a)the unique reference number under which the eligible plant is certified under the Microgeneration Certification Scheme or an equivalent scheme (see paragraph 1(a) and (b) of Schedule 4),

(b)the unique identifier of the boiler upgrade voucher,

(c)the name of the manufacturer, the model, and the serial number of the eligible plant installed for the eligible property F1...,

(d)where the eligible plant installed was a biomass boiler, the biomass emissions certificate,

[F2(da)the date that the eligible plant was commissioned,]

F3(e). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . and

(f)such other information as the Authority may require to enable it to determine the redemption application.