13.—(1) Any permanent and temporary fencing and other means of enclosure for the authorised development must be constructed and installed in accordance with Manual of Contract Documents for Highway Works maintained by or on behalf for the undertaker except where any departures from that manual are agreed in writing by the Secretary of State in connection with the authorised development, following consultation by the undertaker with the relevant highways authority to the extent that it relates to matters relevant to its function.
(2) No part of the new loop road forming Work No. 6 or the new A12 eastbound off-slip forming Work No. 2 is to be opened for traffic until any appropriate measures for the control of deer, including deer fencing, identified following consultation with the relevant planning authority and relevant highway authority on matters related to its function has been installed.
Commencement Information
I1Sch. 2 para. 13 in force at 6.6.2022, see art. 1