The M25 Junction 28 Development Consent Order 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes to legislation:

There are currently no known outstanding effects for the The M25 Junction 28 Development Consent Order 2022, Paragraph 4. Help about Changes to Legislation

Construction Environmental Management PlanE+W

4.—(1) No part of the authorised development is to commence until a CEMP, in accordance with the Outline CEMP, for that part has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority, relevant highway authority and the Environment Agency to the extent that it relates to matters relevant to its functions.

(2) The CEMP must be written in accordance with ISO14001 and, so far as is relevant to that part of the authorised development, must be in accordance with the relevant mitigation measures set out in the REAC, and must include the following management plans—

(a)pollution prevention plan;

(b)dust noise and nuisance management plan;

(c)ecological habitats and species plan;

(d)invasive species management plan;

(e)surface water management plan;

(f)contaminated land management plan;

(g)soil handling management plan;

(h)material management plan;

(i)site waste management plan;

(j)material, waste storage and refuelling plan;

(k)energy and resource use management plan;

(l)emergency response plan; and

(m)community engagement plan.

(3) The construction of the authorised development must be carried out in accordance with the approved CEMP.

(4) A HEMP must be developed and completed by the end of the construction, commissioning and handover stage of the authorised development, in accordance with the process set out in the approved CEMP.

(5) The authorised development must be operated and maintained in accordance with the HEMP.

Commencement Information

I1Sch. 2 para. 4 in force at 6.6.2022, see art. 1