The M25 Junction 28 Development Consent Order 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Paragraph 9

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The M25 Junction 28 Development Consent Order 2022, Paragraph 9. Help about Changes to Legislation

Archaeological remainsE+W

9.—(1) No part of the authorised development is to commence until an archaeological management plan has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority to the extent that it relates to matters relevant to its functions.

(2) The archaeological management plan must be in accordance with the Outline Archaeological Management Plan and reflect the relevant mitigation measures set out in the REAC.

(3) The authorised development must be carried out in accordance with the approved archaeological management plan referred to in sub-paragraph (1).

Commencement Information

I1Sch. 2 para. 9 in force at 6.6.2022, see art. 1