SCHEDULES

Article 34

SCHEDULE 8E+WLAND OF WHICH TEMPORARY POSSESSION ONLY MAY BE TAKEN

(1)

Plot Reference Number shown on Land Plans

(2)

Purpose for which temporary possession may be taken

(3)

Relevant part of the authorised development

Land Plans – Sheet 1 of 4
1/1Construction works relating to improvements to the A12 eastbound carriageway.Work No. 1
1/1bConstruction works relating to improvements to the A12 westbound carriageway.Work No. 4
1/1cConstruction works relating to improvements to the A12 westbound carriageway and to the diversion of an existing underground high pressure gas pipeline.Work Nos. 4 and 29
1/1dConstruction works relating to improvements to the A12 westbound carriageway and to the diversion of an existing underground high pressure gas pipeline.Work Nos. 4 and 29
1/2Construction works relating to improvements to the A12 eastbound carriageway.Work No. 1
1/7Construction works relating to improvements to the A12 westbound carriageway and to the diversion of an existing underground high pressure gas pipeline.Work Nos. 4 and 29
1/8aConstruction works relating to the diversion of an existing underground high pressure gas pipeline.Work No. 29
1/11To establish an environmental bund and construction compound and to undertake associated construction activities.Work No. 18 and, in respect of the construction compound, all works
1/14Construction works relating to the provision of accommodation works for Maylands Golf Course.Work No. 32
1/15Construction works relating to the establishment of a new attenuation pond with associated drainage works and the realignment of a stretch of Weald Brook.Work Nos. 21B, 22 and 23C
1/16Construction works relating to the realignment of stretches of Weald Brook.Work Nos. 23A and 23B
1/17Construction works relating to the new loop road.Work No. 6
1/21aConstruction works relating to the realignment of stretches of Weald Brook.Work Nos. 23A and 23B
1/26Construction working area for alterations to the existing egress from Grove Farm.Work No. 15
1/28aConstruction working area for alterations to the existing egress from Grove Farm.Work No. 15
Land Plans – Sheet 3 of 4
3/2Construction working area for improvements to the M25 northbound carriageway, the realignment of the existing northbound on-slip and a new gantry.Work Nos. 7, 8 and 10
3/3Construction working area for improvements to the M25 northbound carriageway, the realignment of the existing northbound on-slip and a new gantry.Work Nos. 7, 8 and 10
3/6Construction working area for a new gantry.Work No. 10
3/7Construction working area for a new gantry.Work No. 10
3/16Construction working area for improvements to the M25 northbound carriageway, the realignment of the existing northbound on-slip, and a new private means of access.Work Nos. 8 and 14
3/18To establish an ecological mitigation area.Work No. 25
3/19Construction working area for improvements to the M25 northbound carriageway, the realignment of the existing northbound on-slip, and a new private means of access.Work Nos. 8 and 14
3/21Construction works relating to the provision of accommodation works for Maylands Golf Course and to establish an ecological mitigation area.Work Nos. 25 and 32
3/23Construction works relating to the provision of accommodation works for Maylands Golf Course.Work No. 32