The Electricity (Individual Exemptions from the Requirement for a Generation Licence) (Scotland) Order 2022
Citation, commencement and extent1.
(1)
This Order may be cited as the Electricity (Individual Exemptions from the Requirement for a Generation Licence) (Scotland) Order 2022 and comes into force on 19th July 2022.
(2)
This Order extends to England and Wales and Scotland.
Interpretation2.
In this Order —
“the Act” means the Electricity Act 1989;
“Creag Riabhach Wind Farm” means the electricity generating station known as Creag Riabhach Wind Farm, located north of Lairg, and south of Altnaharra, Scotland, incorporating a substation whose entrance is situated at Ordnance Survey map reference NC529273;
“Creag Riabhach Wind Farm Limited” means the company of that name registered in Scotland with company number SC424471;
“licensed generator” means the holder of a licence under section 6(1)(a) of the Act;
“Sandy Knowe Wind Farm” means the electricity generating station known as Sandy Knowe Wind Farm, located south-west of Kirkconnel and Kelloholm, Scotland, incorporating a substation whose entrance is situated at Ordnance Survey map reference NS710100;
“Sandy Knowe Wind Farm Limited” means the company of that name registered in England and Wales with company number 06850950;
Exemption from prohibition of unlicensed generation of electricity for supply3.
Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to—
(a)
Creag Riabhach Wind Farm Limited in respect of Creag Riabhach Wind Farm; and
(b)
Sandy Knowe Wind Farm Limited in respect of Sandy Knowe Wind Farm.
Conditions on exemption granted by article 3(a)4.
The exemption granted by article 3(a) of this Order is subject to compliance with the following conditions—
(a)
Creag Riabhach Wind Farm is connected to the total system;
(b)
Creag Riabhach Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Creag Riabhach Wind Farm Limited; and
(c)
Creag Riabhach Wind Farm Limited is not a licensed generator in respect of Creag Riabhach Wind Farm.
Conditions on exemption granted by article 3(b)5.
The exemption granted by article 3(b) of this Order is subject to compliance with the following conditions—
(a)
Sandy Knowe Wind Farm is connected to the total system;
(b)
Sandy Knowe Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Sandy Knowe Wind Farm Limited; and
(c)
Sandy Knowe Wind Farm Limited is not a licensed generator in respect of Sandy Knowe Wind Farm.
Article 3 of this Order grants exemptions from the requirements of section 4(1)(a) of the Electricity Act 1989 (which prohibits the generation of electricity for supply to any premises without a licence) in relation to two electricity generating stations located in Scotland. The companies granted exemptions are:
Creag Riabhach Wind Farm Limited in respect of Creag Riabhach Wind Farm, an electricity generating station located north of Lairg, and south of Altnaharra, Scotland, incorporating a substation whose entrance is situated at Ordnance Survey map reference NC529273.
Sandy Knowe Wind Farm Limited in respect of Sandy Knowe Wind Farm, an electricity generating station located south-west of Kirkconnel and Kelloholm, Scotland, incorporating a substation whose entrance is situated at Ordnance Survey map reference NS710100.
A regulatory impact assessment in respect of exemptions from the requirements of section 4(1)(a) of the Electricity Act 1989 was prepared in 2001 and can be obtained from the Department for Business, Energy and Industrial Strategy, 1 Victoria Street, London SW1H 0ET. Copies have been placed in the libraries of both Houses of Parliament.