20.—(1) In each scheme year, a compulsory scheme electricity supplier must incur spending under this Part to the amount of its non-core spending obligation.
(2) In doing so, the supplier—
(a)must include spending under Chapter 3 (industry initiatives), subject to the requirements and limits in paragraphs (3) to (5);
(b)may include spending under Chapter 4 (activities specified by the Secretary of State).
(3) Where the aggregate non-core spending obligation for the scheme year exceeds £10 million, the amount of spending on financial assistance under regulation 21 which a supplier counts towards its non-core spending obligation—
(a)must be no less than the obligation percentage of £5 million, but
(b)must not, in total, exceed the obligation percentage of £10 million.
(4) Where the aggregate non-core spending obligation for the scheme year exceeds £6 million, the amount of spending on debt write-off under regulation 21 which a supplier counts towards its non-core spending obligation—
(a)must not exceed the obligation percentage of £3 million in respect of customers who are supplied with neither electricity or gas through a pre-payment meter;
(b)must not, in total, exceed the obligation percentage of £6 million.
(5) Where the aggregate non-core spending obligation for the scheme year exceeds £8 million, the amount of spending on the installation of boilers or central heating systems under regulation 21 which a supplier counts towards its non-core spending obligation must not in total exceed the obligation percentage of £8 million.
(6) In this regulation—
“financial assistance” means the activity listed in the final entry in the table in Part 1 of Schedule 2;
“obligation percentage”, in relation to a supplier, means the percentage determined in accordance with paragraph (3) of regulation 17.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: