77.  In addition to article 2 (interpretation), the terms in this Part have the following meanings—

ENGL” means EDF Energy Nuclear Generation Limited (company number 03076445);

NSL” means a nuclear site licence granted by the Office for Nuclear Regulation in exercise of powers contained in sections 1(1), 3 and 4 of the Nuclear Installations Act 1965;;

Service Media” means pipes, sewers, drains (including drainage ditches) underground and overhead electricity cables, busbars, telecommunications and fibre optic cables, mains, ducts, conduits, gutters, watercourses, wires, other cables, conducting media including any fixings, louvres, cowls and other covers, manholes, junction boxes and other ancillary works and mechanisms;

Site” means any land within the Order Limits in which ENGL has a freehold or leasehold interest.