Compensation
8.—(1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the works referred to in paragraph 5(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a statutory undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any statutory undertaker, the undertaker must—
(a)bear and pay on demand the cost reasonably incurred by that statutory undertaker in making good such damage or restoring the supply; and
(b)make reasonable compensation to that statutory undertaker for any other expenses, loss, demands or proceedings, damages, claims, penalty or costs incurred by the statutory undertaker,
by reason or in consequence of any such damage or interruption.
(2) Nothing in paragraph 8(1) must impose any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the neglect or default of a statutory undertaker, its officers, servants, contractors or agents.
(3) A statutory undertaker must give the undertaker reasonable prior written notice of any claim or demand, and no settlement or compromise may be made without the consent of the undertaker.