SCHEDULE 19Protective Provisions

PART 8FOR THE PROTECTION OF THE NUCLEAR DECOMMISSIONING AUTHORITY AND MAGNOX LIMITED

Indemnity95

1

Subject to sub-paragraph (3), if by reason, or in consequence, of the construction, use, existence, operation or failure of any specified works or in consequence of the construction, use, existence, operation, maintenance or failure of any of the authorised development by or on behalf of the undertaker or in any consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, any damage is caused to any installations or property of NDA and / or Magnox (as applicable), or to operations, or there is any interruption in any service provided to NDA and / or Magnox (as applicable) or by NDA and / or Magnox (as applicable), or in the supply of any goods to NDA and / or Magnox (as applicable) or by NDA and / or Magnox (as applicable) or NDA and / or Magnox (as applicable) becomes liable to pay any amount to any third party, the undertaker must—

a

subject to paragraph 93, bear and pay on demand the proper and reasonable costs reasonably and properly incurred by NDA and / or Magnox (as applicable) in making good such damage or restoring operations, services or supply provided NDA and / or Magnox (as applicable) has obtained the undertaker’s prior approval for any such costs incurred (not to be unreasonably withheld or delayed); and

b

indemnify NDA and / or Magnox (as applicable) for any other expenses, loss (whether direct or indirect and including losses of an economic nature), demands, proceedings, damages, claims penalty or costs incurred by or recovered from NDA and / or Magnox (as applicable) by reason or in consequence of any such damage or interruption or NDA and / or Magnox (as applicable) becoming so liable to any third party as aforesaid other than arising from any default of NDA and / or Magnox (as applicable).

2

The fact that any act or thing may have been done by either NDA or Magnox on behalf of the undertaker or in accordance with a plan approved by NDA and / or Magnox (as applicable) or in accordance with any requirement of NDA and / or Magnox (as applicable) or its supervision does not (subject to sub-paragraph (3)) excuse the undertaker from liability under sub-paragraph (1) unless NDA and / or Magnox (as applicable) fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and NDA and / or Magnox (as applicable) in writing.

3

Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any loss, damage, injury or interruption to the extent that it is attributable to the neglect or default of either NDA or Magnox, its officers, servants, contractors or agents.

4

NDA and / or Magnox (as applicable) must give the undertaker reasonable written notice (being not less than 28 working days) of any claim or demand and, subject to sub-paragraph (5), NDA and / or Magnox (as applicable) may decide whether or not to pass conduct of any proceedings necessary to rest the claim or demand to the undertaker.

5

Where NDA and / or Magnox (as applicable) decides—

a

to retain conduct of any proceedings necessary to rest the claim or demand, NDA and / or Magnox (as applicable) must consult with the undertaker and have due regard to the undertakers’ representations as to how the proceedings are to be conducted and no settlement, admission of liability or compromise may be made without the consent of the undertaker (not to be unreasonably withheld or delayed);

b

to pass conduct of any proceedings necessary to rest the claim or demand to the undertaker, the undertaker must consult with NDA and / or Magnox (as applicable) and have due regard to NDA and / or Magnox’s representations (as applicable) as to how the proceedings are to be conducted and no settlement, admission of liability or compromise may be made without the consent of NDA and / or Magnox (as applicable) (not to be unreasonably withheld or delayed).

6

Neither NDA, Magnox nor the undertaker may make any public statement relating to any claim or demand or any settlement or compromise that may be made in respect of any claim or demand without the consent of NDA, Magnox or the undertaker (as applicable).

7

NDA and / or Magnox (as applicable) must, in respect of any matter covered by the indemnity given by the undertaker in this paragraph, at all times act reasonably and in the same manner as it would as if settling third party claims on its own behalf from its own funds.

8

NDA and / or Magnox (as applicable) must use its reasonable endeavours to mitigate and to minimise any costs, expenses, losses, demands, and penalties to which the indemnity under this paragraph applies where it is within NDA and / or Magnox (as applicable)’s reasonable ability and control to do so and, if reasonably requested to do so by the undertaker, NDA and / or Magnox (as applicable) must provide an explanation of how the claim has been minimised, where relevant.