SCHEDULE 21Deemed Marine Licence under Part 4 (Marine Licensing) of the Marine and Coastal Access Act 2009
PART 3CONDITIONS
Pre-construction7
1
No licensed activity must commence until a detailed and up-to-date programme of works has been submitted to and approved by the MMO in writing. The programme of works must include—
a
a planned timetable for each activity as outlined in paragraphs 4 and 5 of Part 2 of this licence;
b
timings for mobilisation of construction plant and for delivery of materials by sea;
c
a plan for notifying the MMO of the commencement and cessation of activities and phases of activities; and
d
a plan for notifying the MMO of changes to the programme.
2
An updated programme of works must be submitted to the MMO in writing every 6 months from the date of approval unless otherwise agreed with the MMO.