The Sizewell C (Nuclear Generating Station) Order 2022

Article 82

SCHEDULE 23Certified Documents

(1) Document title(2) Document reference
Access Road Plan2.13
Approved Plans2.5 – 2.12
Associated Development Design Principles10.1
Book of Reference4.3
Code of Construction Practice10.2
Construction Method Statement10.3
Deed of Obligation10.4
Deed of Variation (13 April 2022)
Deed of Variation (6 May 2022)
Draft Coastal Processes Monitoring and Mitigation Plan10.5
Draft Fen Meadow Plan10.6
Draft Fish Impingement and Entrainment Monitoring Plan10.7
Draft Marine Mammal Mitigation Protocol10.8
Draft Rail Noise Mitigation Plan10.9
Draft Sabellaria Reef Management and Monitoring Plan10.10
Draft Site Integrity Plan10.11
Draft Water Monitoring and Management Plan10.12
Draft Wet Woodland Plan10.13
Drainage Strategy10.14 (rev 2.0)
EA1N Order Limits Interaction – Offshore Plan2.14
EA1N Sizewell Gap Transport Interaction Plan2.15
EA2 Order Limits Interaction – Offshore Plan2.16
EA2 Sizewell Gap Transport Interaction Plan2.17
Environmental Statement6.1 – 6.20
Estate Wide Management Plan10.15
Fen Meadow Strategy10.16
Land Plans2.1
Lighting Management Plan10.17
Main Development Site Design and Access Statement10.18
Main Development Site Operational Siting and Height Parameters10.19
Main Development Site Water Monitoring and Response Strategy10.20
On-site Marsh Harrier Compensatory Habitat Strategy10.21
Outline Landscape and Ecology Management Plan10.22
Outline Vessel Management Plan10.23
Overarching Archaeological Written Scheme of Investigation10.24
Parameter Plans2.5, 2.6, 2.7 and 2.11
Peat Strategy10.25
Rights of Way and Access Strategy10.26
Rights of Way Plans2.4
Sizewell Link Road Landscape and Ecology Management Plan10.27
Terrestrial Ecology Monitoring and Mitigation Plan10.28
Two Village Bypass Landscape and Ecology Management Plan10.29
Westleton Marsh Harrier Compensatory Habitat Strategy10.30
Wet Woodland Strategy10.31
Works Plans2.3