14.—(1) A measure meets the condition in this article if—

(a)the measure is installed as part of an ECO4 project at private rented premises for which the pre-project SAP band is band E, F or G;

(b)the premises meet the household eligibility requirement specified in article 13(2); and

(c)the measure is—

(i)solid wall insulation;

(ii)a renewable heating system, except where it replaces a renewable heating system of the same kind at the domestic premises;

(iii)a first time heating system;

(iv)a district heating connection; or

(v)an insulation measure installed in order to meet the minimum insulation requirement in article 24 or 25 in relation to a heating measure falling within paragraphs (ii) to (iv).

(2) A measure also meets the condition in this article if—

(a)the measure is installed as part of the same ECO4 project as a measure which is a qualifying action by virtue of meeting the condition in paragraph (1); and

(b)the measure is not the repair or replacement of—

(i)a boiler;

(ii)a central heating system; or

(iii)an electric storage heater.