The Electricity and Gas (Energy Company Obligation) Order 2022

Addition to annual cost savings for projects including repairs and replacements of efficient electric storage heatersE+W+S

This section has no associated Explanatory Memorandum

57.—(1) This article applies for the purpose of determining the value of “ESH” in the formula in article 55(2).

(2) Where the ECO4 project includes one or more qualifying actions specified in paragraph (4), “ESH” is the sum of the determined cost savings for those qualifying actions.

(3) Where the ECO4 project does not include any qualifying actions specified in paragraph (4), “ESH” is £0.

(4) The qualifying actions specified in this paragraph are—

(a)the repair of an efficient electric storage heater; or

(b)the replacement of an efficient electric storage heater with another efficient electric storage heater.

Commencement Information

I1Art. 57 in force at 27.7.2022, see art. 1(1)