Citation and commencement
1. This Order may by cited as the Able Marine Energy Park Development Consent (Amendment) Order 2022 and comes into force on 6th August 2022.
Amendment of the Able Marine Energy Park Development Consent Order 2014
2.—(1) The Able Marine Energy Park Development Consent Order 2014 is amended as follows.
(2) In article 2 (interpretation)—
(a)in the definition of “the berthing pocket”, for the co-ordinates substitute “(53°39.492’N, 00°13.466’W), (53°39.476’N, 00°13.511’W), (53°39.488’N, 00°13.546’W), (53°39.528’N, 00°13.421’W) (53°39.397’N, 00°13.249’W), (53°39.415’N, 00°13.211’W), (53°38.974’N, 00°12.631’W), (53°38.947’N, 00°12.676’W), (53°38.928’N, 00°12.724’W), (53°38.945’N, 00°12.746’W), (53°38.965’N, 00°12.702’W), (53°39.389’N, 00°13.260’W) and (53°39.369’N, 00°13.304’W)”; and
(b)in the appropriate place insert—
““the inset berth” means the area bounded by co-ordinates (53°39.492’N, 00°13.466’W), (53°39.511’N, 00°13.409’W), (53°39.392’N, 00°13.253’W) and (53°39.369’N, 00°13.304’W) and shown on sheets 8 and 9 of the works plans;”.
(3) In Schedule 1 (authorised development), in paragraph 3(a), after “berthing pockets” insert “and inset berth”.
(4) In Schedule 10 (limits of harbour)—
(a)for the table in paragraph 1, substitute—
Table
Latitude | Longitude | Label |
---|---|---|
53°38.965’N | 00°12.701’W | H1 |
53°38.985’N | 00°12.657’W | H2 |
53°39.525’N | 00°13.367’W | H3 |
53°39.492’N | 00°13.465’W | H4 |
53°39.370’N | 00°13.304’W | H5 |
53°39.390’N | 00°13.260’W | H6 |
(b)after the table, for the plan showing the harbour limits substitute the plan in Schedule 1 (harbour limits).
(5) In paragraph 6 of Schedule 11 (requirements)(1)—
(a)in sub-paragraph (a), after “TR030001/APP/23a” insert “and TR030006/APP/16”;
(b)in sub-paragraph (a)(i), for ““AME-02006 (Rev E)”” substitute ““AME-036-20001 (Rev B)””;
(c)in sub-paragraph (a)(ii), for ““AME-02007 (Rev C)”” substitute ““AME-036-20002 (Rev B)””;
(d)in sub-paragraph (a)(iii), for ““AME-02008 (Rev B)”” substitute ““AME-036-20003 (Rev A)””;
(e)in sub-paragraph (a)(v), for ““AME-02010 (Rev B)”” substitute ““AME-036-20004 (Rev B)””;
(f)in sub-paragraph (a)(vi), for ““AME-02011”” substitute ““AME-02011 (Rev C)””;
(g)omit sub-paragraph (a)(xii);
(h)in sub-paragraph (b), for “TR030001/APP/23b” substitute “TR030006/APP/17”;
(i)in sub-paragraph (b)(i), for ““AMEP_P1D_D_001”” substitute ““AME-036-10001 (Rev C)””;
(j)in sub-paragraph (b)(ii), for ““AMEP_P1D_D_002”” substitute ““AME-036-10002 (Rev B)””;
(k)in sub-paragraph (b)(iii), for ““AMEP_P1D_D_005”” substitute ““AME-036-10005 (Rev B)””;
(l)in sub-paragraph (b)(iv), for ““AMEP_P1D_D_006”” substitute ““AME-036-10006 (Rev B)””;
(m)in sub-paragraph (b)(v), for ““AMEP_P1D_D_007”” substitute ““AME-036-10007 (Rev B)””;
(n)in sub-paragraph (b)(vi), for ““AMEP_PID_D_009”” substitute ““AME-036-010008 (Rev C)””;
(o)in sub-paragraph (b)(vii), for ““AMEP_P1D_D_101”” substitute ““AME-036-10009 (Rev C) or AME-036-10009 (Rev D)””;
(p)in sub-paragraph (b)(viii), for ““AMEP_P1D_D_102”” substitute ““AME-036-10010 (Rev C) or AME-036-10010 (Rev D)””;
(q)in sub-paragraph (b)(ix), for ““AMEP_P1D_D_103”” substitute ““AME-036-10011 (Rev C)””;
(r)in sub-paragraph (b)(x), for ““AMEP_PID_D_104”” substitute ““AME-036-10012 (Rev C)”” and at the end, after the semi-colon insert “and”;
(s)in sub-paragraph (b)(xi), for ““AMEP_PID_D_105”” substitute ““AME-036-01013 (Rev C)””;
(t)omit sub-paragraph (b)(xii) and (xiii);
(u)in sub-paragraph (c), for “TR030001/APP/23b” substitute “TR030006/APP/17”;
(v)in sub-paragraph (c)(i), for ““AMEP_PID_D_003”” substitute ““AME-036-10003 (Rev B)””; and
(w)in sub-paragraph (c)(ii), for ““AMEP_P1D_D_004”” substitute ““AME-036-10004 (Rev C)””.
(6) After article 55A (certification of further environmental documents)(2), insert—
“Certification of additional plans etc.
55B.—(1) The undertaker must, as soon as practicable after the making of the Able Marine Energy Park Development Consent (Amendment) Order 2022, submit for certification copies of—
(a)the substitute design drawings, being those drawings with reference TR030006/APP/17;
(b)the updated ecology plans, being those plans with reference TR030006/APP/14;
(c)the updated rights of way plans, being those plans with reference TR030006/APP/15;
(d)the updated environmental statement, being those documents with reference TR030006/APP/6 and TR030006/APP/6A;
(e)the updated habitats regulations assessment, being those documents with reference TR030006/APP/7A, TR030006/APP/7B and TR030006/APP/7C; and
(f)the updated works plans, being those plans with reference TR030006/APP/13.
(2) A plan or document so certified by the Secretary of State is admissible in any proceedings as evidence of the contents of the document of which it is a copy.”.
Signed by authority of the Secretary of State for Transport
Natasha Kopala
Head of the Transport and Works Act Orders Unit
Department for Transport
16th July 2022