12.—(1) No part of the ecological works is to commence until the siting, design, method of construction and timetable for delivery of the new ponds and ditches to be included within Work Nos. 56 and 97 have been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority and Natural England.
(2) The construction of the ponds and ditches forming part of the ecological works must thereafter be carried out in accordance with the approved details.
Commencement Information
I1Sch. 2 para. 12 in force at 2.9.2022, see art. 1