- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made).
15.—(1) No operations consisting of piling or other intrusive works (including drilling) are to commence until a risk assessment and a method statement have been submitted to and approved in writing by the relevant planning authority following consultation with the Environment Agency and Southern Water.
(2) Operations subject to sub-paragraph (1) must be carried out in accordance with the method statement approved under sub-paragraph (1).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: