Search Legislation

The A428 Black Cat to Caxton Gibbet Development Consent Order 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for: Section 25

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The A428 Black Cat to Caxton Gibbet Development Consent Order 2022, Section 25. Help about Changes to Legislation

Compulsory acquisition of land – incorporation of the mineral codeE+W

25.  Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981(1) are incorporated into this Order subject to the following modifications—

(a)paragraph 8(3) is not incorporated;

(b)for “the acquiring authority” substitute “the undertaker”; and

(c)for “undertaking” substitute “authorised development”.

Commencement Information

I1Art. 25 in force at 8.9.2022, see art. 1

Back to top

Options/Help