Construction hours

19.—(1) Construction work for the authorised development must only take place between 0700 hours and 1800 hours Monday to Friday, and 0700 hours to 1300 hours on Saturdays, with no activity on Sundays or bank holidays, except as specified in paragraphs (2) and (3).

(2) Outside the hours and days specified in paragraph (1), daily start up and shut down is permitted and construction work may be undertaken for essential activities comprising—

(a)bridge and gantry demolition and installation including the installation of safety systems;

(b)works over and adjacent to the East Coast Main Line railway;

(c)lifting operations;

(d)site clearance of vegetation adjacent to live carriageways;

(e)site clearance of signs, street furniture and lighting columns adjacent to live carriageways;

(f)any oversize deliveries or deliveries where daytime working would be excessively disruptive to normal traffic operation, including delivery of plant;

(g)junction and highway tie-in works;

(h)installation of temporary and permanent line markings;

(i)traffic management measures and signal changes;

(j)installation of signs and technology;

(k)any emergency works or operations required for safe working;

(l)completion of activities already begun which require continuous periods of operation, such as completing concrete pouring; or

(m)non-intrusive environmental and engineering surveys.

(3) Outside the hours and days specified in paragraph (1), the undertaker may with the prior written consent of the relevant planning authority carry out the following activities—

(a)concrete pours and piling, diaphragm wall works, pavement operations;

(b)work associated with the diversion of existing utilities, including the removal of overhead power lines;

(c)earthworks operations, including excavation, filling, transport, placing and compacting of earthworks material;

(d)intrusive environmental and engineering surveys; or

(e)activities assessed in the environmental statement or which would not give rise to new or materially different effects from those assessed in the environmental statement which do not fall within paragraph (2).

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources