xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
156. [F1Subject to paragraphs 154 and 155], where the undertaker requires to carry out any future specified work then the undertaker must—
(a)provide the Company with not less than 1 calendar month notification of its intention to carry out any such future specified work;
(b)provide the Company with all such reasonable information concerning the future specified work and the procedures for the conduct of the future specified work as the Company may reasonably require and [F2the provisions of paragraphs 142 to 153 shall apply to any such future specified work mutatis mutandis except that—
(i)the time period for providing a method statement under paragraph 142 must be 1 calendar month prior to the commencement of (ii)-the future specified work;
(ii)the time period for approving a method statement under paragraph 143 must be 15 working days;
(iii)the time period for advising the anticipated dates of commencement and completion of the future specified work under paragraph 147 must be 10 working days.]
Textual Amendments
F1Words in Sch. 9 para. 156 substituted (17.7.2024) by The Awel y Môr Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/799), art. 1, Sch.
F2Words in Sch. 9 para. 156(b) substituted (17.7.2024) by The Awel y Môr Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/799), art. 1, Sch.
Commencement Information
I1Sch. 9 para. 156 in force at 11.10.2023, see art. 1