2023 No. 1117

Public Procurement

The Public Procurement (Agreement on Government Procurement) (Thresholds) (Amendment) Regulations 2023

Made

Laid before Parliament

Coming into force

The Minister for the Cabinet Office makes these Regulations in exercise of the powers conferred by regulations 5A and 84A(7) of the Public Contracts Regulations 20151, regulations 9A and 65ZA(6) of the Concession Contracts Regulations 20162 and regulations 16A and 119A(7) of the Utilities Contracts Regulations 20163.

Citation, commencement and extent 1

1

These Regulations may be cited as the Public Procurement (Agreement on Government Procurement) (Thresholds) (Amendment) Regulations 2023 and come into force on 1st January 2024.

2

The amendments made by these Regulations have the same extent as the provisions to which they relate.

Amendments to the Public Contracts Regulations 2015 2

1

The Public Contracts Regulations 2015 are amended as follows.

2

In regulation 54 (threshold amounts), in paragraph (1)—

a

in sub-paragraph (a), for “£5,336,937” substitute “£5,372,609”;

b

in sub-paragraph (b), for “£138,760” substitute “£139,688”;

c

in sub-paragraph (c), for “£213,477” substitute “£214,904”.

Amendment to the Concession Contracts Regulations 2016 3

1

The Concession Contracts Regulations 2016 are amended as follows.

2

In regulation 95 (threshold amounts and methods for calculating the estimated value of concession contracts) in paragraph (1) for “£5,336,937” substitute “£5,372,609”.

Amendments to the Utilities Contracts Regulations 2016 4

1

The Utilities Contracts Regulations 2016 are amended as follows.

2

In regulation 166 (threshold amounts), in paragraph 1—

a

in sub-paragraph (a), for “£426,955” substitute “£429,809”;

b

in sub-paragraph (b), for “£5,336,937” substitute “£5,372,609”.

Transitional provisions 5

1

Nothing in these Regulations affects any procurement commenced before these Regulations come into force.

2

For the purposes of paragraph (1), a procurement is commenced before these Regulations come into force if, before that date, in accordance with the applicable Procurement Regulations—

a

a notice has been submitted to the UK e-notification service in order to—

i

invite offers or requests to be selected to tender for or to negotiate in respect of a proposed contract, framework agreement or dynamic purchasing system; or

ii

publicise an intention to hold a design contest;

b

the contracting authority or utility has had published any form of advertisement seeking offers or expressions of interest in a proposed contract, framework agreement or dynamic purchasing system; or

c

the contracting authority or utility has contacted any economic operator in order to—

i

seek expressions of interest or offers in respect of a proposed contract, framework agreement or dynamic purchasing system; or

ii

respond to an unsolicited expression of interest or offer received from that economic operator in relation to a proposed contract, framework agreement or dynamic purchasing system.

3

For the purposes of this regulation, a procurement covers the whole of the procedures which, in accordance with the applicable Procurement Regulations, stem from that commencement.

4

Procedures taken for the purpose of modifying a contract or framework agreement are not to be regarded, for the purposes of paragraph (3), as stemming from the commencement of the procurement from which the award of that contract or framework agreement had itself stemmed.

5

A procedure commenced as described in paragraph (2)(a)(i), (b) or (c) is not to be regarded, for the purposes of paragraph (3), as stemming from the commencement of any design contest that had previously been held in relation to the subject-matter of the procurement.

6

In this regulation—

a

Procurement Regulations” means the following and, in relation to any procedure, means whichever of the following applies to that procedure—

i

the Defence and Security Public Contracts Regulations 20117;

ii

the Public Contracts Regulations 2015;

iii

the Concession Contracts Regulations 2016;

iv

the Utilities Contracts Regulations 2016;

b

the following have the same meaning as in the applicable Procurement Regulations—

i

contracting authority;

ii

design contest;

iii

dynamic purchasing system;

iv

economic operator;

v

framework agreement;

vi

procurement;

vii

UK e-notification service;

viii

utility.

Alex BurghartMinister for the Cabinet Office
EXPLANATORY NOTE

(This note is not part of the Regulations)

These Regulations make amendments to United Kingdom public procurement regulations to update certain financial thresholds, which govern the procedures for the award of public contracts for goods, works and services. These amendments follow a review of those thresholds in accordance with regulation 5A of the Public Contracts Regulations 2015, regulation 9A of the Concession Contracts Regulations 2016 and regulation 16A of the Utilities Contracts Regulations 2016. This review was previously undertaken by the European Commission to ensure the thresholds continue to correspond with the relevant thresholds laid down in the World Trade Organisation’s Agreement on Government Procurement (“GPA”). Following the United Kingdom’s exit from the EU, and subsequent accession to the GPA8 as a member in its own right, this review requirement was conferred on the Minister for the Cabinet Office by the Public Procurement (Amendment etc.) (EU Exit) Regulations 20209.