Statutory Instruments
Infrastructure Planning
Made
31st January 2023
Coming into force
1st February 2023
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008 (the “2008 Act”)(1), to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (the “2011 Regulations”)(2) for a non-material change to the Immingham Open Cycle Gas Turbine Order 2020 (the “2020 Order”)(3).
The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2020 Order.
Accordingly, the Secretary of State, in exercise of the powers in paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—
1. This Order may be cited as the Immingham Open Cycle Gas Turbine (Amendment) Order 2023 and comes into force on 1stFebruary 2023.
2. The Immingham Open Cycle Gas Turbine Order 2020 is amended in accordance with this Order.
3. In article 2 (interpretation) of Part 1 (preliminary) in the definition of “commissioning”, after the words “the undertaker’s operational and safety requirements”, insert “and the words “commission” and “commissioned” and cognate expressions are to be construed accordingly;”.
4. In Schedule 1 (authorised development), in the description of Work No. 1—
(a)at the end of sub-paragraph (u) delete “and”; and
(b)at the end of sub-paragraph (v) insert—
“and
(w)synchronous condenser.”.
5. In Schedule 2 (requirements), in paragraph 11 sub-paragraph (3) after the words “No part of the authorised development may commence” insert “save for the permitted preliminary works”.
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
David Wagstaff
Deputy Director – Energy Development and Resilience
Department for Business, Energy and Industrial Strategy
31st January 2023
(This note is not part of the Order)
This Order amends the Immingham Open Cycle Gas Turbine Order 2020, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008. The Order allows for the addition of a Synchronous Condenser in the description of Work No.1 in Schedule 1, and the amendment of Requirement 11(3) in Schedule 2 of the Order in relation to the submission of the flood risk mitigation scheme.
2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 to the Localism Act 2011 (c. 20), and by section 28 of the infrastructure Act 2015 (c. 7). There are other amendments to the Act that are not relevant to this Order.
S.I. 2011/2055, as amended by S.I. 2012/635, S.I. 2015/760 and S.I. 2020/1534. There are other amendments to the instrument which are not relevant to this Order.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: