Modification of contracts and framework agreements during their term

This section has no associated Explanatory Memorandum

13.—(1) Subject to paragraph (3), a contract or framework agreement for relevant health care services may be modified during its term without following a new procurement process under these Regulations only where—

(a)the modification is clearly and unambiguously provided for in the contract or framework agreement documents,

(b)the modification is solely a change in the identity of the provider due to succession into the position of provider following corporate changes including takeover, merger, acquisition or insolvency and the relevant authority is satisfied that the provider meets the basic selection criteria,

(c)the modification is made in response to external factors beyond the control of the relevant authority and the provider including, but not limited to—

(i)changes in patient or service user volume, or

(ii)changes in prices in accordance with a formula provided for in the contract documents,

and the modification does not render the contract or framework agreement materially different in character, or

(d)the modification is attributable to a decision of the relevant authority and both of the criteria in paragraph (2) are met.

(2) The criteria are—

(a)the modification does not render the contract or framework agreement materially different in character, and

(b)the cumulative change in the lifetime value of the contract or framework agreement since it was entered into or concluded is—

(i)below £500,000; or

(ii)less than 25% of the lifetime value of the original contract or framework agreement when it was entered into or concluded.

(3) Where Direct Award Process A or Direct Award Process B was followed for the original award of a contract, the contract may be modified during its term without following a new procurement process under these Regulations where the modification does not render the contract materially different in character.

(4) Where—

(a)a modification is made to a contract or framework agreement without following a new procurement process, in accordance with paragraph (1) or (3),

(b)the modification is attributable to a decision of the relevant authority, and

(c)the cumulative change in the lifetime value of the contract since it was entered into, or framework agreement since it was concluded, is £500,000 or more,

the relevant authority must submit a notice of the modification for publication on the UK e-notification service.

(5) The notice in paragraph (4) must—

(a)be submitted for publication within 30 days of the modification of the contract or framework agreement, and

(b)include the information set out in Schedule 12.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources