Parish of Thornhaugh | 1/1a | Temporary storage and working area to support construction of the following in adjoining land parcels: a new private means of access to 4 properties, diversion, protection and removal of potable water pipes and the protection of the NGG gas pipeline including the crossing of Work No. 2. | 2, 3, 4 |
Parish of Thornhaugh | 1/1c | Temporary storage and working area to support construction of the following in adjoining land parcels: a new private means of access to 4 properties, diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, and overhead and underground electricity cables. | 2, 3 |
Parish of Thornhaugh | 1/1e | Temporary storage and working area to support construction of the following in adjoining land parcels: diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, overhead and underground electricity cables crossing Work No. 2 and
protection of NGG gas pipeline.
| 3, 4 |
Parish of Thornhaugh | 1/3a | Temporary storage and working area to support construction of the following in adjoining land parcels: diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, and overhead and underground electricity cables and adjacent utility works. | 3 |
Parish of Thornhaugh | 1/3c | Temporary storage and working area to support construction of the following in adjoining land parcels: diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, and overhead and underground electricity cables and adjacent utility works. | 3 |
Parish of Thornhaugh | 1/9a | Protection, diversion and removal of existing water pipes, electricity and telecommunications cables and associated apparatus
Temporary storage and working area to support construction of the following in
adjoining land parcels: new private means of access to 4 properties and a service vehicle turning point including earthworks and associated drainage.
Temporary storage and working area to support construction of the following in
adjoining land parcels: diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, and overhead and underground electricity cables and adjacent utility works.
| 2, 3 |
Parish of Thornhaugh | 1/10a | Temporary storage and working area to support construction of the following in adjoining land parcels: diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, and overhead and underground electricity cables and adjacent utility works. | 3, 5 |
Parish of Wansford | 2/1d | Temporary protection of electricity and telecommunications cables and associated apparatus.
Temporary storage and working area to support construction of the following in adjoining land parcels: improvement to the eastbound carriageway of the existing A47 including the realignment of the central reserve and a new cycle crossing point at the Wansford western roundabout.
| 12 |
Parish of Thornhaugh | 2/3b | Temporary storage and working area to support construction of the following in adjoining land parcels: new carriageway to create a free flow link from A1 southbound to the dualled A47 eastbound including embankments and associated drainage.
Temporary storage and working area to support diversion and removal of underground electronic communication cables and apparatus and adjacent utilities works.
| 5, 6 |
Parish of Wansford | 3/1c | Temporary protection of electricity and telecommunications cables and associated apparatus.
Temporary storage and working area to support construction of the following in adjoining land parcels new carriageway to create a free flow link from A1 southbound to the dualled A47 eastbound including embankments and associated drainage.
Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline including earthworks and associated drainage.
Temporary storage and working area to support diversion, protection and removal of potable water pipes, electronic communication cables and apparatus, and overhead and adjacent utilities works.
| 1, 2, 6 |
Parish of Wansford | 3/1j | Temporary protection of electronic communications cables and associated apparatus.
Temporary access to facilitate construction of the following in adjoining land parcels: diversion and removal of electronic communication cables and apparatus and diversion of water pipes and construction of a site office and construction areas.
| 16 |
Parish of Wansford | 3/1l | Temporary protection of water pipes, sewers, electricity and telecommunications cables and associated apparatus.
Temporary access to facilitate construction of the following in adjoining land parcels: diversion and removal of electronic communication cables and apparatus and diversion of water pipes and construction of a site office and construction areas.
| 16 |
Parish of Wansford | 3/1o | Temporary protection of electronic communications cables and associated apparatus.
Temporary access to facilitate construction of the following in adjoining land parcels: diversion and removal of electronic communication cables and apparatus and diversion of water pipes and construction of a site office and construction areas.
| 16 |
Parish of Wansford | 3/2c | Temporary welfare and compound area including a haul route. | 24 |
Parish of Wansford | 3/2e | Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the existing A47 including earthworks and associated drainage.
Temporary storage and working area to facilitate construction of the following in adjoining land parcels: a new Sacrewell Farm access road connecting to Work No. 15 and running north passing through the Sacrewell Farm underbridge including earthworks and drainage.
Temporary welfare and compound area including a haul route.
| 1, 21, 24 |
Parish of Wansford | 3/2i | Temporary protection of water pipes and associated apparatus.
Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the termination point to the east for tie into existing A47 including earthworks and associated drainage.
Temporary storage and working area to facilitate construction of the following in adjoining land parcels: a new Sacrewell Farm access road connecting to Work No. 15 and running north passing through the Sacrewell Farm underbridge including earthworks and drainage.
Temporary welfare and compound area including a haul route.
| 1, 21, 24 |
Parish of Wansford | 3/2k | Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the termination point to the east for tie into existing A47 including earthworks and associated drainage.
Temporary welfare and compound area including a haul route.
| 1, 24 |
Parish of Wansford | 3/3d | Temporary storage and working area to support provision of a new Sacrewell Farm access road connecting to Work No. 15 and running north passing through the Sacrewell Farm underbridge including earthworks and drainage. | 23 |
Parish of Wansford | 3/3g | Temporary storage and working area to support provision of a new Sacrewell Farm access road connecting to Work No. 15 and running north passing through the Sacrewell Farm underbridge including earthworks and drainage and access link to Sacrewell Farm. | 23 |
Parish of Wansford | 3/4h | Temporary protection of electronic communications cables and associated apparatus.
Temporary access to facilitate construction of the following in adjoining land parcels: diversion and removal of electronic communication cables and apparatus and diversion of water pipes, provision of a site office and construction area and a new Sacrewell Farm Underbridge under the dualled A47 (Work No. 1) including structural units, concrete foundations, drainage and waterproofing.
| 16, 25 |
Parish of Wansford | 3/4i | Temporary protection of electronic communications cables and associated apparatus.
Temporary access to facilitate construction of the following in adjoining land parcels: diversion and removal of electronic communication cables and apparatus and diversion of water pipes, provision of a site office and construction area and
protection, diversion and resilience works to large diameter water pipelines and associated apparatus and adjacent utility works.
| 16, 27 |
Parish of Wansford | 3/5a | Temporary storage and working area to facilitate construction of the following in adjoining land parcels: the removal of underground electricity cables crossing Work Nos. 1, 8, 10, 11, 13, 16, 17, 21 and 26, and improvements to the existing A1/A47 on and off ramps to the Wansford east roundabout including earthwork widening. | 9, 11, 27 |
Parish of Wansford | 4/2b | Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the existing A47 including earthworks and associated drainage, the provision of support for a new balancing pond to the north of the dualled A47 (Work No. 1) including drainage inlets, an outlet to river Nene and an access track.
Temporary storage and working area to support the diversion and removal of overhead electrical cables and adjacent utilities works.
| 1, 28, 29 |
Parish of Wansford and Parish of Sutton | 4/2f | Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the existing A47 including earthworks and associated drainage and adjacent utilities works. | 1, 16, 26 |
Parish of Sutton | 4/2i | Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the termination point to the existing A47 including earthworks and associated drainage and adjacent utilities works and provision of a new balancing pond to the north of the dualled A47 (Work No. 1) including drainage inlets, an outlet to river Nene and an access track. | 1, 16, 26, 27, 28 |
Parish of Wansford | 4/3d | Temporary storage to facilitate construction of the following in adjoining land parcels: the dualling of the A47 mainline from the existing Wansford eastern roundabout to the existing A47 including earthworks and associated drainage, a new length of carriageway to form a new link road from A47 Wansford eastern roundabout (Work No. 13) and a new A47 westbound off slip from the dualled A47 (Work No. 1) including earthworks, associated drainage and a cycle track, and adjacent utilities works. | 1, 15, 16, 29 |
Parish of Wansford | 4/3f | Temporary storage and working area to support diversion and removal of overhead electrical cables crossings and utilities works in adjoining land parcels. | 29 |
Parish of Sutton | 4/5b | Temporary storage and working area to support diversion and removal of electronic communication cables and apparatus and utilities works in adjoining land parcels. | 36 |
Parish of Sutton | 4/6b | Temporary storage and working area to support diversion and removal of overhead electrical cables crossings and utilities works in adjoining land parcels. | 29, 32 |
Parish of Sutton | 4/9a | Temporary access route from Work No. 37 turning to temporary welfare and compound area including a haul road to the north of the dualled A47 (Work No. 1) and a new temporary access track from Work No. 37. | 38 |
Parish of Sutton | 5/3a | Temporary storage and working area to facilitate construction of the following in adjoining land parcels: new Sutton Heath House roundabout (Work No. 44) north to Sutton Heath Road including earthworks and drainage and access points. | 42 |
Parish of Sutton | 5/3b | Temporary storage and working area to facilitate construction of the following in adjoining land parcels: new Sutton Heath House roundabout (Work No. 44) north to Sutton Heath Road including earthworks and drainage and access points. | 42 |
Parish of Upton | 5/4d | Temporary storage and working area to support diversion of electronic overhead and underground communication cables and apparatus crossings in adjoining land parcels. | 56 |
Parish of Upton | 5/5b | Temporary storage and working area to support improvements to the existing Upton Drift including passing places and other works in adjoining land parcels. | 55 |
Parish of Upton | 5/6a | Temporary storage and working area to support construction of the following in adjoining land parcels: improvements to the existing Upton Drift including passing places, widening the metalled surface into highway verge, straightening of the S- bend and sight lines and widening of its existing junction with Langley Bush Road and the existing junction adjacent to Model Farm. | 55 |
Parish of Upton | 5/6c | Temporary storage and working area to support improvements to the existing Upton Drift including passing places in adjoining land parcels. | 55 |
Parish of Upton | 5/6e | Temporary storage and working area to support improvements to the existing Upton Drift including passing places and connected works in adjoining land parcels. | 55 |
Parish of Upton | 5/6g | Temporary storage and working area to support diversion of electronic overhead and underground communication cables and apparatus crossings in adjoining land parcels. | 56 |
Parish of Upton | 5/6h | Temporary storage and working area to support diversion of electronic overhead and underground communication cables and apparatus crossing in adjoining land parcels. | 56 |
Parish of Upton | 5/6k | Temporary storage and working area to support diversion of the underground cables and protection of the foul sewer crossings in adjoining land parcels. | 58 |
Parish of Upton | 5/6l | Temporary storage and working area to support improvements to the existing Upton Drift including passing places, widening the metalled surface into highway verge, straightening of the S- bend and sight lines and widening of its existing junction with Langley Bush Road and the existing junction adjacent to Model Farm including earthworks and drainage in adjoining land parcels. | 55 |
Parish of Upton | 5/7a | Temporary storage and working area to support improvements to the existing Upton Drift including passing places, widening the metalled surface into highway verge, straightening of the S- bend and sight lines and widening of its existing junction with Langley Bush Road and the existing junction adjacent to Model Farm including earthworks and drainage in adjoining land parcels. | 55 |
Parish of Upton | 5/7c | Temporary storage and working area to support improvements to the existing Upton Drift including passing places, widening the metalled surface into highway verge, straightening of the S- bend and sight lines and widening of its existing junction with Langley Bush Road and the existing junction adjacent to Model Farm including earthworks and drainage in adjoining land parcels. | 55 |
Parish of Upton | 5/8a | Temporary storage and working area to support diversion of the underground cables and protection of the foul sewer crossings in adjoining land parcels. | 58 |
Parish of Sutton | 6/1e | Temporary storage and working area to support with the creation of a new turning head to the existing Drift with gated access for service providers for 250 metres including earthworks, drainage, sub-base layers, pavement, signage, fence and gates in adjoining land parcels. | 47 |
Parish of Sutton | 6/2a | Temporary storage and working area to support a new access route from Work No. 37,
temporary welfare and compound area including haul road to the north of the dualled A47 in adjoining land parcels.
| 38 |
Parish of Sutton | 6/3f | Temporary storage and working area to support creation of new turning head to the existing drift with gated access for service providers for 250 metres including earthworks, drainage, sub-base layers, pavement, signage, fence, and gates in adjoining land parcels. | 47 |
Parish of Sutton | 6/3h | Temporary storage and working area to support diversion and removal of existing electronic communication cables and apparatus, underground electricity cables, and utility works in adjoining land parcels. | 48 |
Parish of Sutton | 6/4a | To support access route from Work No. 37.
Temporary welfare and compound area including haul road to the north of the dualled A47 (Work No. 1).
To support diversion and removal of electronic communication cables and apparatus, electrical cables and potable water pipes and adjacent utility works in adjoining land parcels.
| 36, 38 |
Parish of Sutton | 6/4e | Temporary storage and working area to support a new access route from Work No. 37.
Temporary welfare and compound area including haul road to the north of the dualled A47 (Work No. 1) and a new temporary access track from Work No. 37.
| 38 |
Parish of Sutton | 6/4g | Temporary storage and working area to support a new access route from Work No. 37. Temporary welfare and compound area including haul road to the north of the dualled A47 (Work No. 1) and a new temporary access track from Work No. 37.
Temporary storage and working area to facilitate the protection, diversion and resilience works to potable water pipes and associated apparatus and adjacent utility works in adjoining land parcels.
| 38, 49 |
Parish of Sutton | 6/5b | Temporary storage and working area to support the following in adjoining land parcel: diversion, and removal of existing electronic communication cables and apparatus, underground electricity cables, and adjacent utility works, ecological works and provision of landscaping area to the south of the dualled A47. | 39, 48 |
Parish of Sutton | 6/5e | Temporary storage and working area to support alterations to The Drift in adjoining land parcels. | 47 |
Parish of Sutton | 7/3a | Temporary storage and working area to support alterations to The Drift and to facilitate the protection, diversion and resilience works to potable water pipes and associated apparatus and utility works in adjoining land parcels. | 47, 49 |
Parish of Sutton | 7/4b | Temporary storage and working area to support alterations to The Drift and to support diversion and removal of existing electronic communication cables and apparatus, underground electricity cables, and potable water pipes and utility works in adjoining land parcels. | 47, 48 |