Located at the A1 side road, next to the proposed access to the properties on the A1.
H2 shown on sheet 1 of the Hedgerow Plans.
| Partial removal | Work nos. 2, 3 and 4 |
Located at A1 side road.
H3 shown on sheet 2 of the Hedgerow Plans.
| Full removal | Work nos. 5, 6 and 7 |
Located at the pond maintenance track next to the new proposed free flow link road from the A1 to the A47.
H4 and H6 shown on sheets 3 of the Hedgerow Plans.
| Partial removal | Work nos. 9 and 10 |
Located at the proposed Sacrewell Farm Access Road.
H7 shown on sheet 3 of the Hedgerow Plans.
| Partial removal | Work no. 21 |
Located at the existing A47 near the proposed Sacrewell Farm Access Road.
H9 shown on sheet 3 of the Hedgerow Plans.
| Partial removal | Work nos. 1, 8, 9, 17 and 21 |
Located at the existing A47 nearby the proposed Sacrewell Farm Access Road.
H11 and H13 on sheet 3 of the Hedgerow Plans.
| Partial removal | Work nos. 8, 17 and 21 |
Located at the existing A47 near the existing Sacrewell Farm link road.
H15 shown on sheets 3 and 4 of the Hedgerow Plans.
| Partial removal | Work nos. 1, 15, 16, 27 and 28 |
Located at the existing A47 near the existing Sacrewell Farm link road.
H16 shown on sheet 3 of the Hedgerow Plans.
| Full removal | Work nos. 8, 15, 16, 26 and 27 |
Located at the existing A47 where it overlaps with the proposed A47.
H17 shown on sheet 4 of the Hedgerow Plans.
| Full removal | Work nos. 1, 15, 16, 28, 29, 30, 33, 36 and 40 |
Located at the existing A47 where it overlaps with the proposed A47.
H19 shown on sheet 4 of the Hedgerow Plans.
| Partial removal | Work nos. 1, 16 and 28 |
Located at the new link to Sutton Heath Road and Langley Bush Road.
H21 shown on sheet 5 of the Hedgerow Plans.
| Partial removal | Work nos. 36, 42 and 43 |
Located near the new A47 Sutton Roundabout.
H29 shown on sheet 6 of the Hedgerow Plans.
| Partial removal | Work nos. 1 and 38 |
Located at the new link to Sutton Heath Road.
H31 shown on sheet 6 of the Hedgerow Plans.
| Partial removal | Work nos. 36 and 42 |
Located at the new A47 Sutton roundabout.
H33 shown on sheet 6 of the Hedgerow Plans.
| Partial removal | Work nos. 1, 36 and 46 |
Located at the proposed A47 dual carriageway.
H35 shown on sheet 6 of the Hedgerow Plans.
| Partial removal | Work nos. 1 and 49 |
Located at the proposed A47 dual carriageway.
H38 shown on sheet 7 of the Hedgerow Plans.
| Partial removal | Work nos. 1 and 48 |
Located at the existing A47 where it is used as cycle path/footway.
H39 shown on sheet 6 of the Hedgerow Plans.
| Partial removal | Work nos. 36 and 40 |
Located at the new link with Peterborough Road.
H42 shown on sheet 6 and 7 of the Hedgerow Plans.
| Partial removal | Work nos. 45, 48 and 49 |
Located at the new pond near Nene Way.
H44 shown on sheet 7 of the Hedgerow Plans.
| Partial removal | Work nos. 48 and 50 |
Located at the new link with Peterborough Road.
H46 shown on sheet 7 of the Hedgerow Plans.
| Partial removal | Work nos. 45, 48 and 50 |
Located at the new link with Peterborough Road
H49 shown on sheet 7 of the Hedgerow Plans.
| Partial removal | Work nos. 45, 48, 50 and 52 |
Located at the proposed A47 dual carriageway.
H51 shown on sheet 7 of the Hedgerow Plans.
| Partial removal | Work nos. 1 and 48 |
Located at Upton Road.
H53 shown on sheet 7 of the Hedgerow Plans.
| Partial removal | Work nos. 53 and 54 |
Located at Upton Road.
H54 shown on sheet 7 of the Hedgerow Plans.
| Full removal | Work nos. 53 and 54 |
Located at Upton Drift.
H55 and H56 shown on sheet 5 (Inset 5B) of the Hedgerow Plans.
| Full removal | Work nos. 55, 56, 57 and 58 |