1

This Instrument may be cited as the Hampshire County Council (M27 Junction 10) (Slip Roads, Special Roads) Scheme 2022 Confirmation Instrument 2023 and shall come into force on the date on which notice that it has been confirmed is first published in accordance with paragraph 1 of Schedule 2 to the Highways Act 1980.

2

The Hampshire County Council (M27 Junction 10) (Slip Roads, Special Roads) Scheme 2022 (“the Scheme”) is hereby confirmed without modifications.

3

The Scheme as confirmed is set out in the Schedule hereto and copies of the Scheme with its accompanying plan are deposited at the offices of the Secretary of State for Transport and at the offices of The Hampshire County Council at Hampshire Legal Services, Hampshire County Council, Corporate Services, EII South, The Castle, Winchester, Hampshire SO23 8UJ.

Signed by Authority of the Secretary of State

Martin GilmourA Senior Civil Servant in the Department for Transport