7.—(1) The Secretary of State must, no later than the scheme introduction date, determine and publish, in respect of each scheme period, the scheme parameters for the electricity scheme and for the gas scheme.
(2) The “scheme parameters” are—
(a)a price (the “government supported price”, in p/kWh)—
(i)for general supply contracts and ETII supply contracts;
(ii)for QHS supply contracts;
(b)the amount (the “GSP decrement”, in p/kWh) of a decrease in the government supported price, to be applied in relation to ETII supply contracts;
(c)an amount (the “maximum discount”, in p/kWh) which is the maximum amount of any discount—
(i)for general supply contracts and ETII supply contracts;
(ii)for QHS supply contracts;
(d)the amount (the “MD increment”, in p/kWh) of an increase in the maximum discount, to be applied in relation to ETII supply contracts;
(e)the amount (the “minimum supply price”, in p/kWh) which is the minimum discounted supply price—
(i)for general supply contracts and ETII supply contracts;
(ii)for QHS supply contracts.
(3) The Secretary of State may, in respect of either scheme period, for the purposes of the electricity scheme or the gas scheme, revise any scheme parameter by publishing a notice that specifies—
(a)the revised scheme parameter;
(b)the date, which must not be earlier than the date of publication, with effect from which the revision is made (“revision date”);
(c)whether the revision applies in respect of—
(i)variable price contracts, flexible price contracts or fixed price contracts, and
(ii)in the case of variable price contracts or flexible price contracts, to those contracts entered into before the revision date.
(4) A revised scheme parameter—
(a)applies in respect of supply contracts entered into on or after the revision date;
(b)does not apply in respect of fixed price contracts entered into before that date;
(c)applies, where so specified under paragraph (3)(c)(ii), in respect of variable price contracts or flexible price contracts entered into before that date;
(d)does not in any case apply in respect of energy supplied under a supply contract before that date.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: