5.—(1) Subject to sub-paragraphs (2) and (3), any difference arising between the conservancy authority and the company in respect of the matters set out in this Schedule must be determined by an arbitrator to be agreed upon between the parties.
(2) If the parties cannot agree on an arbitrator, the arbitrator is to be appointed by the President of the Institution of Civil Engineers on the application of either party.
(3) The party making an application under sub-paragraph (2) must give notice in writing to the other party prior to making the application.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: