xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

Article 2

SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Interpretation

1.—(1) In this Schedule—

biodiversity units” means the product of the size of an area, and the distinctiveness and condition of the habitat it comprises to provide a measure of ecological value (as assessed using the Defra biodiversity off–setting metric);

biodiversity off-setting scheme” means a scheme which will deliver biodiversity enhancements which must not be less than the off–setting value;

Defra” means the Department for Environment, Food and Rural Affairs;

“Defra biodiversity off–setting metric” means the mechanism published by Defra to quantify impacts on biodiversity, which allows biodiversity losses and gains affecting different habitats to be compared and ensures offsets are sufficient to compensate for residual losses of biodiversity;

heavy commercial vehicle” has the meaning given by section 138 (meaning of “heavy commercial vehicle”) of the 1984 Act(1);

“mean high water springs” or “MHWS” means the highest level which spring tides reach on average over a period of time;

off-setting value” means the net biodiversity impact of the authorised development, calculated using the Defra biodiversity off–setting metric, measured in biodiversity units; and

wharf outage” means circumstances caused by factors beyond the undertaker’s control in which waste, clay or sediment has not or could not be received at Work No. 4 for a period in excess of four consecutive days.

(2) References in this Schedule to part of the authorised development are to be construed as references to stages, phases or elements of the authorised development in respect of which an application is made by the undertaker under this Schedule, and references to commencement of part of the authorised development in this Schedule are to be construed accordingly.

(3) References to details or schemes approved under this Schedule are to be construed as references to details or schemes approved in relation to a specified part of the authorised development, as the case may be.

Time limits

2.—(1) The authorised development must commence within 5 years of the date on which this Order is made.

(2) The authorised development must not commence unless the undertaker has given the relevant planning authorities one month’s notice of its intention to commence the authorised development.

Detailed design approval

3.—(1) The authorised development must be designed in detail and carried out in accordance with the design principles contained in the design and access statement and the preliminary scheme design shown on the indicative generating station plans and indicative wharf plans, unless otherwise agreed in writing by the relevant planning authority, following consultation with the Environment Agency to the extent that it relates to matters relevant to its function, provided that the relevant planning authority is satisfied that any amendments to those documents showing departures from the preliminary scheme design would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

(2) Where amended details are approved by the relevant planning authority under sub-paragraph (1), those details are deemed to be substituted for the corresponding indicative generating station plans and indicative wharf plans the undertaker must make those amended details available in electronic form for inspection by members of the public. The amended details must be implemented as approved.

Detailed design (appearance)

4.—(1) In relation to any part of the authorised development comprised in Work Nos. 1, 2, 3, 4 and 5 no development of that part may commence until details of the external appearance, including the colour, materials and surface finishes, of all new permanent buildings and structures have been submitted to and approved by the relevant planning authority.

(2) The authorised development must be carried out in accordance with the approved details.

Parameters of authorised development

5.  The elements of the authorised development listed in column (1) of the table below (design parameters) must not exceed the maximum dimensions and levels and, where applicable, the minimum dimensions, set out in relation to that element in columns (3) to (6) of that table.

(1)

Element of authorised development

(2)

Work No.

(3)

Maximum length (metres)

(4)

Maximum width (metres)

(5)

Maximum height (metres) from ground level unless stated

(6)

Minimum height (metres) from ground level unless stated

Main energy recovery facility buildings (3  No. units, dimensions per unit)1A1053544
Energy recovery stacks (3  No.)1A(a)(iv)8080
Turbine building1A(a)(v)534020
Air cooled condenser array1A(a)(vii)654530
Ash processing building1B703032
Carbon dioxide recovery building1C302012
Lightweight aggregates main building2754044
Lightweight aggregates storage silos2(a), 2(e)6625
Lightweight aggregates stacks (2  No.) 2(d)8080
Electrical substation39535
Wharf structure4(a)4007.2 (AOD)
Supporting buildings and facilities (control room, visitor centre, workshops)5402015

Landscape and ecological mitigation strategy

6.—(1) No part of the authorised development may commence until a landscape and ecological mitigation strategy for that part has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency, the relevant statutory nature conservation body, Lincolnshire Wildlife Trust and the Royal Society for the Protection of Birds.

(2) The relevant planning authority’s approval of the landscape and ecological mitigation strategy is restricted to those parts of the strategy that relate to the parts of the authorised development that are above MHWS, with the remainder the strategy approved by the MMO under condition 18 of Schedule 9 (deemed marine licence).

(3) The landscape and ecological mitigation strategy approved under sub-paragraph (1) must be substantially in accordance with the outline landscape and ecological mitigation strategy.

(4) The landscape and ecological mitigation strategy approved under sub-paragraph (1) must include details of—

(a)mitigation measures required to protect protected habitats and species, non–statutory designated sites and other habitats and species of principal importance during the construction of the authorised development;

(b)mitigation measures required to protect protected habitats and species, non–statutory designated sites and other habitats and species of principal importance during the operation of the authorised development;

(c)the results of the Defra biodiversity off-setting metric together with the off-setting value required, the nature of such off-setting and evidence that the off–setting value provides for the required biodiversity compensation, risk factors (including temporal lag) and long term management and monitoring;

(d)the site or sites on which the compensation off–setting required pursuant to (c) will be provided together with evidence demonstrating that the site or sites has/have been chosen in accordance with the prioritisation set out in the outline landscape and ecological mitigation strategy;

(e)certified copies of the completed legal agreements securing the site or sites identified in (d) to enable enactment of the biodiversity off-setting scheme and the biodiversity off–setting management and monitoring plan as approved in the landscape and ecological mitigation strategy;

(f)any hard and soft landscaping to be incorporated within Work Nos. 1, 2, 3, 4, 5 and 6 including location, number, species, size of any planting and the management and maintenance regime for such landscaping; and

(g)an air quality deposition monitoring plan that must be substantially in accordance with the outline air quality deposition monitoring plan and must include the final numbers and locations of deposition monitoring locations, as agreed with the relevant statutory nature conservation body and the Environment Agency.

(5) The landscape and ecological mitigation strategy must be implemented as approved under sub-paragraph (1).

Archaeology

7.—(1) No part of Work Nos. 1, 2, 3, 4, 5 and 6 may commence until for that part a written scheme of investigation, reflecting the relevant mitigation measures set out in the outline written scheme of investigation has been submitted to and approved by the relevant planning authority, following consultation with Historic England.

(2) The scheme approved under sub-paragraph (1) must—

(a)identify areas where field work or a watching brief are required and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found; and

(b)detail the measures for post-field work processing, assessment analysis and reporting of the results of archaeological work and the deposition of the archive.

(3) Works Nos. 1, 2, 3, 4, 5 and 6 must be carried out in accordance with the scheme referred to in sub-paragraph (1), unless otherwise agreed by the relevant planning authority.

Highway access

8.—(1) No part of Work No. 7 may commence until written details of the siting, design and layout of any new temporary means of access to a highway in that part, or any alteration to an existing means of access to a highway in that part has been submitted to and approved by the relevant planning authority, following consultation with the relevant highway authority.

(2) The highway accesses must be constructed or altered as approved under sub-paragraph (1).

(3) The undertaker must not exercise the power in article 14(1) (permanent stopping up of streets) unless and until a plan showing the layout for the termination of the street (as specified in columns (1) and (2) of Schedule 6) has been submitted to and approved by the relevant planning authority.

Surface and foul water drainage

9.—(1) No part of the authorised development may commence until for that part a surface and foul water drainage strategy has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency, lead local flood authority, Anglian Water Services Limited and relevant internal drainage board to the extent that it relates to matters relevant to their functions.

(2) The strategy submitted for approval under sub-paragraph (1) must be substantially in accordance with the outline surface and foul water drainage strategy.

(3) The surface and foul water drainage strategy must be implemented as approved under sub-paragraph (1) and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.

Contamination

10.—(1) No part of the authorised development may commence until—

(a)intrusive ground investigations have been carried out for the purpose of assessing ground conditions; and

(b)a scheme to deal with the contamination of land, including groundwater, and ground gases which are likely to cause significant harm to persons or pollution of controlled waters or the environment, has, for that part, been submitted to and approved by the relevant planning authority.

(2) The scheme must include a risk assessment, supported by site investigation data, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose.

(3) With respect to ground gases, the risk assessment required under sub-paragraph (2) must adopt the source-pathway-receptor principle to identify plausible contaminant linkages and take into account potential migration of off-site ground gases.

(4) The authorised development, including any remediation, must be carried out in accordance with the approved scheme unless otherwise agreed with the relevant planning authority.

(5) Should any remediation be required a verification report demonstrating the completion of works set out in the approved scheme and the effectiveness of the remediation must be submitted to, and approved, by the relevant planning authority prior to the date of final commissioning.

(6) The verification report submitted for approval under sub-paragraph (5) must include results of sampling and monitoring carried out in accordance with the remediation strategy to demonstrate that the site remediation criteria have been met along with any long-term post-remediation monitoring requirements.

Code of construction practice

11.—(1) No part of the authorised development may commence until a code of construction practice for that part has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency and the relevant statutory nature conservation body to the extent that it relates to matters relevant to their functions.

(2) The code of construction practice submitted for approval must be substantially in accordance with the outline code of construction practice to the extent that it is applicable to that part and must reflect the mitigation measures set out in the register of environmental actions and commitments.

(3) The code of construction practice submitted under sub-paragraph (1) must include the following—

(a)the construction and phasing programme;

(b)liaison procedures;

(c)complaints procedures;

(d)an air quality and dust management plan detailing air quality and dust monitoring and management measures during construction that must be substantially in accordance with the outline air quality and dust management plan;

(e)construction noise and vibration monitoring and management plan;

(f)a site waste management plan detailing sustainable site waste management measures;

(g)a soil management plan detailing measures to ensure the temporary storage of soils and other material of value will be in accordance with best practice;

(h)details of screening and fencing to be installed during construction;

(i)a materials management plan detailing measures to ensure the safe storage of excavated materials during construction;

(j)a pollution prevention and incident response plan detailing measures to prevent and control the spillage of oil, chemicals and other potentially harmful liquids;

(k)a health and safety plan, including details of how health and safety risks are to be identified and managed during construction;

(l)a surface and foul water drainage plan including measures for the protection of surface and groundwater during construction;

(m)an artificial light emissions management plan;

(n)measures to ensure the restoration of site following completion of construction; and

(o)appropriate procedures to address any unexploded ordnance that may be encountered.

(4) All construction works must be undertaken in accordance with the approved code of construction practice.

Construction hours

12.—(1) Construction works relating to the authorised development must not take place on Sundays, bank holidays nor otherwise outside the hours of 0800 to 2000 hours on Monday to Saturday (with the option of 0700 to 1900).

(2) The restrictions in sub-paragraph (1) do not apply to construction works where these—

(a)are carried out within existing buildings or buildings constructed as part of the authorised development;

(b)are carried out with the prior approval of the relevant planning authority;

(c)are associated with an emergency; or

(d)are associated with slip form working.

(3) In this requirement “emergency” means a situation where, if the relevant action is not taken, there will be adverse health, safety, security or environmental consequences that in the reasonable opinion of the undertaker would outweigh the adverse effects to the public (whether individual classes or generally as the case may be) of taking that action.

Construction traffic management plan

13.—(1) No part of the authorised development may commence until a construction traffic management plan for that part has been submitted to and approved by the relevant planning authority, following consultation with the relevant highway authority, Boston Borough Council and the relevant statutory nature conservation body in relation to any proposals under sub-paragraph (2)(d) only.

(2) A construction traffic management plan must be substantially in accordance with the outline construction traffic management plan and must include the following (as applicable for the part of the authorised development to which the construction traffic management plan relates)—

(a)construction vehicle routing plans in respect of both workers and deliveries;

(b)proposals for the scheduling and timing of movements of delivery vehicles including details of abnormal indivisible loads;

(c)site access plans;

(d)where practicable, proposals for temporary diversions of any public rights of way;

(e)measures to ensure the protection of users of any footpath within the Order limits which may be affected by the construction of the authorised development;

(f)proposals for the management of junctions to and crossings of highways and other public rights of way;

(g)a construction logistics plan;

(h)a procedure for reviewing and updating the construction traffic management plan;

(i)a construction worker travel plan, including details of the likely number of worker vehicle movements and the management of workforce parking; and

(j)appropriate procedures to provide for a vehicle booking management system.

(3) The construction traffic management plan submitted pursuant to sub–paragraphs (1) and (2) must be accompanied by a statement and associated junction appraisals (as defined in the outline construction traffic management plan) demonstrating how the likely construction traffic impacts identified in the environmental statement are addressed through the measures contained in the construction traffic management plan.

(4) The construction traffic management plan submitted pursuant to sub–paragraphs (1) and (2) that relates to Work Nos. 1, 2, 3, 4, 5, 6 and 7 must be accompanied by a pre-condition highway survey (as defined in the outline construction traffic management plan).

(5) The construction traffic management plan and any updated construction traffic management plan submitted following any review under sub-paragraph (2)(h) must be implemented as approved by the relevant planning authority.

Flood risk emergency plan

14.—(1) No part of the authorised development may commence until a flood risk emergency plan has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency, Black Sluice Internal Drainage Board and the Lead Local Flood Authority.

(2) The flood risk emergency plan must include—

(a)procedures to receive flood warnings (including communication lines to cover shift patterns and / or staff leave), and closure of or evacuation of the authorised development with sufficient lead time to ensure no personnel or vehicles are left within the Order limits during times of a flood warning; and

(b)identification of areas of emergency refuge to be located above the modelled breach flood depths.

(3) The flood risk emergency plan must be implemented as approved by the relevant planning authority.

Phasing of construction and commissioning of Work Nos. 1 and 2

15.—(1) Subject to sub–paragraph (2), no part of the authorised development may commence until a phasing programme setting out the commencement of construction and the anticipated start of commissioning and the anticipated date of final commissioning for each of Work Nos. 1 and 2 has been submitted to and approved by the relevant planning authority.

(2) The phasing programme must provide for the anticipated date of final commissioning of Work Nos. 1 and 2 as soon as reasonably practicable. The phasing programme must be implemented as approved by the relevant planning authority.

Operational lighting scheme

16.—(1) Prior to the commissioning of any part of Work Nos. 1, 2, 3, 4 and 5 a written scheme for the management and mitigation of operational external artificial light emissions for that part must be submitted to and approved by the relevant planning authority.

(2) The written scheme must be substantially in accordance with the outline lighting strategy.

(3) The scheme for the management and mitigation of operational external artificial light emissions must be implemented as approved under sub-paragraph (1).

Operational vehicle movements

17.—(1) Except in the event of a wharf outage, the number of two-way heavy commercial vehicle movements must not exceed a maximum of 30 two-way vehicle movements per day except in circumstances where, following consultation with the relevant highway authority and Boston Borough Council, the relevant planning authority is satisfied that additional vehicle movements would not give rise to any materially new or materially different highway safety impacts or environmental effects in comparison with those reported in the environmental statement.

(2) Waste must not be delivered by road to Work No. 1A except in the event of a wharf outage or in circumstances where, following consultation with the relevant highway authority and Boston Borough Council, the relevant planning authority is satisfied that such delivery of waste by road would not give rise to any materially new or materially different highway safety impacts or environmental effects in comparison with those reported in the environmental statement.

(3) Clay and sediment must not be delivered by road to Work No. 2 or lightweight aggregates exported by road from Work No. 2 except in the event of a wharf outage or in circumstances where, following consultation with the relevant highway authority and Boston Borough Council, the relevant planning authority is satisfied that such delivery or export by road would not give rise to any materially new or materially different highway safety impacts or environmental effects in comparison with those reported in the environmental statement.

(4) Prior to the date of final commissioning, an operational traffic management plan for that part must be submitted to and approved by the relevant planning authority, following consultation with the relevant highway authority and Boston Borough Council.

(5) The operational traffic management plan must include—

(a)an operational worker travel plan that includes measures to encourage the use of sustainable modes of transport by employees;

(b)measures to manage the routing and number of heavy commercial vehicles during operation;

(c)measures to manage the routing and number of heavy commercial vehicles in the event of a wharf outage;

(d)provision as to the responsibility for, and timescales of, the implementation of those measures; and

(e)a monitoring and review regime.

(6) The operational traffic plan must be implemented as approved under sub-paragraph (4).

Waste hierarchy scheme

18.—(1) Prior to the commissioning of any part of Work No. 1A, the undertaker must submit to the relevant planning authority for approval a scheme, which sets out arrangements for maintenance of the waste hierarchy in priority order and which aims to minimise recyclable and reusable waste received at the authorised development during the commissioning and operational period of the authorised development (the “waste hierarchy scheme”).

(2) The waste hierarchy scheme must include details of—

(a)the type of information that must be collected and retained on the sources of the residual waste after recyclable and reusable waste has been removed;

(b)the arrangements that must be put in place for ensuring that as much reusable and recyclable waste as is reasonably possible is removed from waste to be received at the authorised development, including contractual measures to encourage as much reusable and recyclable waste being removed as far as possible;

(c)the arrangements that must be put in place for ensuring that commercial suppliers of residual waste operate a written environmental management system which includes establishing a baseline for recyclable and reusable waste removed from residual waste and specific targets for improving the percentage of such removed reusable and recyclable waste;

(d)the arrangements that must be put in place for suspending and/or discontinuing supply arrangements from commercial suppliers who fail to retain or comply with any environmental management systems;

(e)the arrangements that must be put in place for the provision of an annual waste composition analysis undertaken by the undertaker, with the findings submitted to the relevant planning authority within one month of the sampling being undertaken; and

(f)the form of records that must be kept for the purpose of demonstrating compliance with (a) to (e) and the arrangements in place for allowing inspection of such records by the relevant planning authority.

(3) The waste hierarchy scheme must be implemented as approved under sub-paragraph (1).

Control of operational noise

19.—(1) Prior to commissioning of any part of Works Nos. 1, 2, 3 and 4 a written noise monitoring scheme must be submitted to and approved by the relevant planning authority, such scheme must specify—

(a)each location from which noise is to be measured;

(b)the method of noise measurement, which must be in accordance with British Standard 4142:2014 +A1:2019;

(c)the maximum permitted levels of noise at each agreed monitoring location which must not exceed the defined limits to demonstrate compliance with government and local policy on noise;

(d)provision requiring the undertaker to take noise measurements as soon as possible following a reasonable request by the relevant planning authority and to submit the measurements to the relevant planning authority as soon as they are available; and

(e)a definition of the circumstances that constitute an emergency for the purposes of sub-paragraphs (2)(a), (3) and (5).

(2) The level of noise at each monitoring location must not exceed the maximum permitted level specified for that location in the scheme, except—

(a)in the case of an emergency (as defined in the noise monitoring scheme);

(b)with the prior approval of the relevant planning authority; or

(c)as a result of steam purging or the operation of emergency pressure relief valves or similar equipment of which the undertaker has given notice in accordance with sub–paragraph (3).

(3) Except in the case of an emergency, the undertaker must give the relevant planning authority 48 hours’ notice of any proposed steam purging or operation of emergency pressure relief valves or similar equipment.

(4) So far as reasonably practicable, steam purging and the operation of emergency pressure relief valves or similar equipment may only take place—

(a)between 0900 and 1700 hours on weekdays (excluding bank holidays); and

(b)between 0900 and 1300 hours on Saturdays (excluding bank holidays).

(5) Where the level of noise at a monitoring location exceeds the maximum permitted level specified for that location in the approved scheme because of an emergency—

(a)the undertaker must, as soon as possible and in any event within two business days of the beginning of the emergency, submit to the relevant planning authority a statement detailing—

(i)the nature of the emergency;

(ii)why it is necessary for the level of noise to have exceeded the maximum permitted level;

(b)if the undertaker expects the emergency to last for more than 24 hours, it must inform local residents and businesses affected by the level of noise at that location of—

(i)the reasons for the emergency; and

(ii)how long it expects the emergency to last.

Notice of start of commissioning and notice of date of final commissioning

20.—(1) Where practicable, notice of the intended start of commissioning of Work No. 1A must be given to the relevant planning authorities prior to such start and in any event within seven days from the date that commissioning is started.

(2) Within seven days of completing final commissioning of Work No. 1A, the undertaker must provide the relevant planning authorities with notice of the date upon which such commissioning was duly completed.

Combined heat and power

21.—(1) On the date that is 12 months after the date of final commissioning for Work No. 1A, the undertaker must submit to the relevant planning authority for its approval, following consultation with Boston Borough Council, a report (“the CHP review”) updating the combined heat and power assessment.

(2) The CHP review submitted and approved must—

(a)consider whether opportunities reasonably exist for the export of heat from numbered Work 1A; and

(b)include a list of actions (if any) that the undertaker is reasonably required to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 1A.

(3) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.

(4) On each date during the operation of Work No. 1A that is five years after the date on which it last submitted the CHP review or a revised CHP review to the relevant planning authority, a revised CHP review must be submitted to and approved by the relevant planning authority, following consultation with Boston Borough Council.

(5) Sub-paragraphs (2) and (3) apply in relation to a revised CHP review submitted under sub-paragraph (4) in the same way as they apply in relation to the CHP review submitted under sub-paragraph (1).

Decommissioning

22.—(1) Within 24 months of the permanent cessation of the operation of Work Nos. 1 and 2 details of a scheme for the restoration and aftercare of the land for Work Nos. 1. 2, 3, 4 (excluding any parts of Work No. 4 that are covered by the decommissioning scheme approved under the deemed marine licence), 5 and 6 must be submitted to and approved by the relevant planning authority.

(2) The scheme must include details of structures and buildings to be demolished or retained, details of the means of removal of materials following demolition, phasing of demolition and removal, details of restoration works and phasing thereof.

(3) The scheme as approved under sub-paragraph (1) must be implemented in accordance with the phasing set out therein.

Amendments to approved details

23.—(1) With respect to the documents certified under article 47 (certification of documents, etc.), the parameters specified in the table in paragraph 5 of this Schedule and any other plans, details or schemes which require approval by the relevant planning authority pursuant to any requirement (together “Approved Documents, Plans, Parameters, Details or Schemes”), the undertaker may submit to the relevant planning authority for approval, following consultation by the undertaker with Lincolnshire County Council, any amendments to the Approved Documents, Plans, Parameters, Details or Schemes and following any such approval by the relevant planning authority the Approved Documents, Plans, Parameters, Details or Schemes are to be taken to include the amendments approved by the relevant planning authority in accordance with this paragraph.

(2) Approval under sub-paragraph (1) for the amendments to Approved Documents, Plans, Parameters, Details or Schemes must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Electricity generation cap

24.—(1) The authorised development must not generate more than 300 megawatts unless otherwise agreed by the relevant planning authority provided that the relevant planning authority is satisfied, following consultation with the relevant statutory nature conservation body to the extent that it relates to matters relevant to its functions, that any increase would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

(2) The undertaker must keep records for the purpose of demonstrating compliance with sub-paragraph (1) and must submit them to the relevant planning authority on an annual basis.

(3) On receipt of a written request to view the records by the relevant planning authority these records must be made available for inspection within seven days of such a request.

(4) References in Schedule 1 (authorised development) to 300 megawatts are to be construed as references to any electricity cap approved under sub-paragraph (1).

Tonnage caps

25.—(1) The total amount of—

(a)waste derived fuel received at Work No. 1A and Work No. 4 must not exceed 1,200,000 tonnes per calendar year;

(b)bottom ash and boiler ash processed at Work No. 1B must not exceed 200,000 tonnes per calendar year; and

(c)aggregate to be processed at Work No. 2 and received at Work No. 4 must not exceed 300,000 tonnes per calendar year,

unless otherwise agreed by the relevant planning authority provided that the relevant planning authority is satisfied, following consultation with the relevant statutory nature conservation body to the extent that it relates to matters relevant to its functions, that any increase would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

(2) The undertaker must keep records for the purpose of demonstrating compliance with sub-paragraph (1) and must submit them to the relevant planning authority on an annual basis.

(3) On receipt of a written request to view the records by the relevant planning authority these records must be made available for inspection within seven days of such a request.

(4) References in Schedule 1 (authorised development) to any tonnage amount are to be construed as references to any tonnage amount approved under sub-paragraph (1).

PART 2PROCEDURE FOR DISCHARGE OF REQUIREMENTS

Applications made under Part 1

26.—(1) Where an application has been made to a relevant planning authority for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement) included in this Order, the relevant planning authority must give notice to the undertaker of its decision on the application within a period of eight weeks beginning with—

(a)the day immediately following that on which the application is received by the relevant planning authority;

(b)the day immediately following that on which further information has been supplied by the undertaker under paragraph 27 (further information); or

(c)such longer period as may be agreed between the parties.

(2) Subject to sub-paragraph (3), in the event that the relevant planning authority does not determine an application within the period set out in sub-paragraph (1), the relevant planning authority is taken to have granted all parts of the application (without any condition or qualification) at the end of that period.

(3) In determining any application made to the relevant planning authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, the relevant planning authority may—

(a)give or refuse its consent, agreement or approval; or

(b)give its consent, agreement or approval subject to reasonable conditions,

and where consent, agreement or approval is refused or granted subject to conditions the relevant planning authority must provide its reasons for that decision with the notice of its decision.

Further information

27.—(1) In relation to any part of an application made under this Schedule, the relevant planning authority has the right to request such further information from the undertaker as it considers necessary to enable it to consider the application.

(2) If the relevant planning authority considers that further information is necessary and the requirement concerned contained in Part 2 of this Schedule does not specify that consultation with a consultee is required, the relevant planning authority must, within ten business days of receipt of the application, notify the undertaker in writing specifying the further information required.

(3) If the requirement concerned contained in Part 1 of this Schedule specifies that consultation with a consultee is required, the relevant planning authority must issue the consultation to the consultee within five business days of receipt of the application, and notify the undertaker in writing specifying any further information requested by the consultee within five business days of receipt of such a request.

(4) If the relevant planning authority does not give the notification within the period specified in sub-paragraph (2) or (3) it (and the consultee, as the case may be) it is deemed to have sufficient information to consider the application and is not entitled to request further information without the prior agreement of the undertaker.

Fees

28.—(1) Where an application is made to the relevant planning authority for written consent, agreement or approval in respect of a requirement, the fee prescribed under regulation 16(1)(b) of the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012(2) (as may be amended or replaced from time to time A) is to apply and must be paid to the relevant planning authority for each application.

(2) Any fee paid under this Schedule must be refunded to the undertaker within four weeks of—

(a)the application being rejected as invalidly made; or

(b)the relevant planning authority failing to determine the application within the decision period as determined under paragraph 26(1),

unless within that period the undertaker agrees, in writing, that the fee is to be retained by the relevant planning authority and credited in respect of a future application.

Register of requirements

29.—(1) The undertaker must, as soon as practicable following the making of this Order, establish and maintain in an electronic form suitable for inspection by members of the public a register of those requirements contained in Part 1 of this Schedule that provide for further approvals to be given by the relevant planning authority.

(2) The register must set out in relation to each such requirement the status of the requirement, in terms of whether any approval to be given by the relevant planning authority has been applied for or given, providing an electronic link to any document containing any approved details.

(3) The register must be maintained by the undertaker for a period of 3 years following completion of the authorised development.

Appeals to the Secretary of State

30.—(1) The undertaker may appeal to the Secretary of State if—

(a)the relevant planning authority refuses an application for any consent, agreement or approval required by—

(i)a requirement and any document referred to in any requirement in Part 1 of this Schedule; or

(ii)any other consent, agreement or approval required under this Order, or grants it subject to conditions to which the undertaker objects;

(b)the relevant authority does not give notice of its decision to the undertaker within the period specified in paragraph 26(1) or grants it subject to conditions;

(c)having received a request for further information under paragraph 27(1) the undertaker considers that either the whole or part of the specified information requested by the relevant planning authority is not necessary for consideration of the application;

(d)having received any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application; or

(e)the relevant planning authority issues a notice further to sections 60 or 61 of the Control of Pollution Act 1974(3).

(2) The appeal process applicable under sub-paragraph (1) is as follows—

(a)any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination, or (where no determination has been made) the expiry of the decision period as determined under paragraph 26;

(b)the undertaker must submit to the Secretary of State a copy of the application submitted to the relevant planning authority and any supporting documents which the undertaker may wish to provide (“the appeal documents”);

(c)the undertaker must on the same day provide copies of the appeal documents to the relevant planning authority and the requirement consultee (if applicable);

(d)as soon as is practicable after receiving the appeal documentation, the Secretary of State must appoint a person to consider the appeal (“the appointed person”) and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for their attention should be sent;

(e)the relevant planning authority and the requirement consultee (if applicable) must submit any written representations in respect of the appeal to the appointed person within 10 business days beginning with the first day immediately following the date on which the appeal parties are notified of the appointment of the appointed person and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;

(f)the appeal parties must make any counter-submissions to the appointed person within 10 business days beginning with the first day immediately following the date of receipt of written representations pursuant to sub-paragraph (e); and

(g)the appointed person must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable.

(3) In the event that the appointed person considers that further information is necessary to enable the appointed person to consider the appeal, the appointed person must as soon as practicable notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.

(4) Any further information required under sub-paragraph (3) must be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person.

(5) The appeal parties may submit written representations to the appointed person concerning matters contained in the further information.

(6) Any such representations must be submitted to the appointed person and made available to all appeal parties within 10 business days of the date mentioned in sub-paragraph (3).

(7) On an appeal under this paragraph, the appointed person may—

(a)allow or dismiss the appeal; or

(b)reverse or vary any part of the decision of the relevant planning authority (whether the appeal relates to that part of it or not) and may deal with the application as if it had been made to the appointed person in the first instance.

(8) The appointed person may proceed to a decision on an appeal taking into account such written representations as have been sent within the relevant time limits and in the sole discretion of the appointed person such written representations as have been sent outside the relevant time limits.

(9) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.

(10) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.

(11) Any consent, agreement or approval given by the appointed person pursuant to this paragraph is deemed to be an approval for the purpose of Part 1 of this Schedule as if it had been given by the relevant planning authority.

(12) The relevant planning authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) does not affect or invalidate the effect of the appointed person’s determination.

(13) Except where a direction is given under sub-paragraph (14) requiring some or all of the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.

(14) On application by the relevant authority or undertaker, the appointed person may give directions as to the costs of the appeal and as to the parties by whom such costs are to be paid.

(15) In considering whether to make any such direction as to the costs of the appeal parties and the terms on which it is to be made, the appointed person must have regard to the relevant Planning Practice Guidance published by the Ministry for Housing, Communities and Local Government or such guidance as may from time to time replace it.

Anticipatory steps towards compliance with any requirement

31.  If before the coming into force of this Order the undertaker or any other person has taken any steps that were intended to be steps towards compliance with any provision of Part 1 of this Schedule, those steps may be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.

Interpretation of Part 2 of Schedule 2

32.  In Part 2 of Schedule 2—

the appeal parties” means the relevant planning authority, the requirement consultee and the undertaker;

business day” means a day other than a Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 1971(4); and

requirement consultee” means any body named in a requirement which is the subject of an appeal as a body to be consulted by the relevant authority in discharging that requirement.