Construction traffic management plan

13.—(1) No part of the authorised development may commence until a construction traffic management plan for that part has been submitted to and approved by the relevant planning authority, following consultation with the relevant highway authority, Boston Borough Council and the relevant statutory nature conservation body in relation to any proposals under sub-paragraph (2)(d) only.

(2) A construction traffic management plan must be substantially in accordance with the outline construction traffic management plan and must include the following (as applicable for the part of the authorised development to which the construction traffic management plan relates)—

(a)construction vehicle routing plans in respect of both workers and deliveries;

(b)proposals for the scheduling and timing of movements of delivery vehicles including details of abnormal indivisible loads;

(c)site access plans;

(d)where practicable, proposals for temporary diversions of any public rights of way;

(e)measures to ensure the protection of users of any footpath within the Order limits which may be affected by the construction of the authorised development;

(f)proposals for the management of junctions to and crossings of highways and other public rights of way;

(g)a construction logistics plan;

(h)a procedure for reviewing and updating the construction traffic management plan;

(i)a construction worker travel plan, including details of the likely number of worker vehicle movements and the management of workforce parking; and

(j)appropriate procedures to provide for a vehicle booking management system.

(3) The construction traffic management plan submitted pursuant to sub–paragraphs (1) and (2) must be accompanied by a statement and associated junction appraisals (as defined in the outline construction traffic management plan) demonstrating how the likely construction traffic impacts identified in the environmental statement are addressed through the measures contained in the construction traffic management plan.

(4) The construction traffic management plan submitted pursuant to sub–paragraphs (1) and (2) that relates to Work Nos. 1, 2, 3, 4, 5, 6 and 7 must be accompanied by a pre-condition highway survey (as defined in the outline construction traffic management plan).

(5) The construction traffic management plan and any updated construction traffic management plan submitted following any review under sub-paragraph (2)(h) must be implemented as approved by the relevant planning authority.

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?