http://www.legislation.gov.uk/uksi/2023/800/schedule/1/paragraph/21/made
The Hornsea Four Offshore Wind Farm Order 2023
en
King's Printer of Acts of Parliament
2023-10-19
INFRASTRUCTURE PLANNING
This Order grants development consent for, and authorises the construction, operation and maintenance of an offshore wind farm generating station located in the North Sea 69 kilometres due east of Flamborough Head at its closest point together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory purchase of land (including rights in land) and the right to use land and to override easements and other rights.
The Hornsea Four Offshore Wind Farm Order 2023
Preamble
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
art. 26(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3A
para. 3
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3A
para. 9(4)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 23(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 23(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 24(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(6)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(10)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(4)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 4
para. 4(1)(r)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 4
para. 12(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 5
para. 1(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(i)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(j)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(o)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(p)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(p)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(q)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 9
para. 8(1)(a)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 10
para. 2(a)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 16
para. 10(a)(v)(cc)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
SCHEDULES
SCHEDULE 1AUTHORISED PROJECT
PART 3REQUIREMENTS
Restoration of land used temporarily for construction21
Any land landward of MLWS within the Order limits which is used temporarily for construction of the connection works and not ultimately incorporated in permanent works or approved landscaping, must be reinstated in accordance with such details as have been submitted to and approved by the relevant planning authority in consultation with, where appropriate, the MMO, and the relevant highway authority, as soon as reasonably practicable and in any event within twelve months of completion of the connection works.