SCHEDULES

SCHEDULE 1AUTHORISED PROJECT

PART 3REQUIREMENTS

Provision of landscapingI18

1

No stage of the connection works may commence until a written landscape management plan and associated work programme (which accords with the outline landscape management plan and outline ecological management plan) for that stage of the connection works has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs and Historic England.

2

The landscape management plan must include details of—

a

surveys, assessments and method statements as guided by BS 5837 and the Hedgerows Regulations 1997;

b

location, number, species, size and planting density of any proposed planting;

c

cultivation, importing of materials and other operations to ensure plant establishment; and

d

implementation timetables for the relevant stage of the landscaping works.

3

The landscape management plan must be carried out as approved.