http://www.legislation.gov.uk/uksi/2023/800/schedule/9/part/11/paragraph/3
The Hornsea Four Offshore Wind Farm Order 2023
en
INFRASTRUCTURE PLANNING
2024-05-20
Statute Law Database
2023-08-03
This Order grants development consent for, and authorises the construction, operation and maintenance of an offshore wind farm generating station located in the North Sea 69 kilometres due east of Flamborough Head at its closest point together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory purchase of land (including rights in land) and the right to use land and to override easements and other rights.
The Hornsea Four Offshore Wind Farm Order 2023
Preamble
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
art. 26(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3A
para. 3
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3A
para. 9(4)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 23(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 23(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 24(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(6)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(10)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(4)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 4
para. 4(1)(r)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 4
para. 12(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 5
para. 1(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(i)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(j)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(o)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(p)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(p)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(q)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 9
para. 8(1)(a)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 10
para. 2(a)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 16
para. 10(a)(v)(cc)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
SCHEDULES
SCHEDULE 9PROTECTIVE PROVISIONS
PART 11FOR THE PROTECTION OF HARBOUR ENERGY LIMITED, PERENCO UK LIMITED, PREMIER OIL E&P UK EU LIMITED, DANA PETROLEUM (E&P) LIMITED AND DANA PETROLEUM LIMITED
Restriction on authorised developmentI13
Prior to the completion of the licensee’s works, no wind turbine generator shall be erected in the marine corridor, the aviation corridor, or in any WTG exclusion zone, unless otherwise agreed in writing between the licensee and the undertaker.