Search Legislation

The Hornsea Four Offshore Wind Farm Order 2023

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Paragraph 5

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Hornsea Four Offshore Wind Farm Order 2023. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

5.—(1) The undertaker must not submit the construction traffic management plan to the relevant planning authority in accordance with requirement 19 (construction traffic management plan) without having first obtained the written approval of Network Rail in respect of all provisions relating to Cranswick Level Crossing, Driffield Level Crossing and safety briefings for HGV drivers on the safe use of level crossings affected by the authorised project in accordance with sub-paragraph (2).E+W+S

(2) The undertaker must provide Network Rail with a draft of the construction traffic management plan for approval and Network Rail must within a period of 28 days beginning with the date on which the draft construction traffic management plan is received by Network Rail and acting reasonably serve written notice on the undertaker confirming that—

(a)the draft construction traffic management plan is approved; or

(b)the draft construction traffic management plan is approved subject to reasonable amendments as required by Network Rail; or

(c)the draft construction traffic management plan is not approved and the reason for the non-approval; or

(d)that further information is required in order for Network Rail to make its determination (in which case this paragraph 5(2) must apply to such further information from the date of its receipt by Network Rail).

(3) In the event that Network Rail fails to serve written notice in accordance with paragraph 5(2) within 28 days of receipt Network Rail is deemed to have served a notice pursuant to paragraph 5(2)(a).

(4) The undertaker must include any reasonable amendments which are required by Network Rail and notified to the undertaker by Network Rail in the notice given pursuant to paragraph 5(2)(b) in the draft construction traffic management plan it submits to the relevant planning authority in accordance with requirement 19 (construction traffic management plan) and the undertaker must not submit any such written details that relate to Cranswick Level Crossing, Driffield Level Crossing and/or safety briefings for HGV drivers on the safe use of level crossings affected by the authorised project to the relevant planning authority which have not been approved by Network Rail in accordance with paragraphs 5(2) or 5(3).

(5) Each notice and all other information required to be sent to Network Rail under the terms of this paragraph 5 must—

(a)be sent to the Company Secretary and General Counsel at Network Rail Infrastructure Limited, 1 Eversholt Street, London, NW1 2DN via Royal Mail plc’s special delivery service (or if this service is no longer being provided an appropriate recorded delivery postal service) and marked for the attention of the Level Crossing Manager; and

(b)contain a clear statement on its front page that Network Rail must respond within 28 days of receipt.

(6) In the event that any subsequent changes are made to the construction traffic management plan following consultation with Network Rail, in so far as such changes impact on railway property, the undertaker must not submit any such written details to the relevant planning authorities or finalise any updates to the construction traffic management plan without further consultation with Network Rail.

Commencement Information

I1Sch. 9 Pt. 4 para. 5 in force at 3.8.2023, see art. 1

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources