http://www.legislation.gov.uk/uksi/2023/800/schedule/9/part/5/paragraph/7
The Hornsea Four Offshore Wind Farm Order 2023
en
INFRASTRUCTURE PLANNING
2024-05-20
Statute Law Database
2023-08-03
This Order grants development consent for, and authorises the construction, operation and maintenance of an offshore wind farm generating station located in the North Sea 69 kilometres due east of Flamborough Head at its closest point together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory purchase of land (including rights in land) and the right to use land and to override easements and other rights.
The Hornsea Four Offshore Wind Farm Order 2023
Preamble
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
art. 26(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3A
para. 3
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3A
para. 9(4)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 23(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 23(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 24(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(6)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 25(10)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(3)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(4)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 3B
para. 26(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 4
para. 4(1)(r)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 4
para. 12(5)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 5
para. 1(2)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(i)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(j)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(o)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(p)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(p)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 7
para. 4(2)(q)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 9
para. 8(1)(a)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 9 Pt. 10
para. 2(a)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
The Hornsea Four Offshore Wind Farm Order 2023
Sch. 16
para. 10(a)(v)(cc)
The Hornsea Four Offshore Wind Farm (Correction) Order 2024
Sch.
art. 1(2)
SCHEDULES
SCHEDULE 9PROTECTIVE PROVISIONS
PART 5FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
I17
If by reason of construction of the specified work the Agency’s access to flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow the Agency to maintain the flood defence or use the equipment no less effectively than was possible before the obstruction within 24 hours of the undertaker becoming aware of such obstruction.