Removal of apparatus and rights for alternative apparatus

31.—(1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or over which access to any apparatus is enjoyed or requires that any apparatus is relocated or diverted, that apparatus must not be removed by the undertaker and any right of Esso to maintain and use that apparatus in that land and to gain access to it must not be extinguished until alternative apparatus has been constructed and is in operation, and access to it has been provided, to the reasonable satisfaction of Esso.

(2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give Esso 56 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Esso reasonably needs to remove any apparatus) the undertaker must, subject to sub-paragraph (3), afford to Esso the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently grant alternative rights for the maintenance of that apparatus in accordance with paragraph (6).

(3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, the undertaker must afford to and, if necessary, acquire for the benefit of Esso the necessary facilities and rights for the construction, maintenance and use of the alternative apparatus and access to it.

(4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Esso and the undertaker or in default of agreement settled by arbitration in accordance with article 57 (arbitration).

(5) Esso must, after the alternative apparatus to be provided or constructed has been agreed or settled in accordance with article 57 (arbitration), and after the grant to Esso of any such facilities and rights as are referred to in sub-paragraph (2), proceed as soon as reasonably practicable using reasonable endeavours to construct and bring into operation the alternative apparatus and subsequently to remove (or if agreed between the parties allow the undertaker to remove) any redundant apparatus required by the undertaker to be removed under the provisions of this Schedule.

(6) Irrespective of sub-paragraph (5), if the undertaker gives notice in writing to Esso that it desires itself to execute any work, or part of any work in connection with the construction, removal or decommissioning of apparatus in the land of the undertaker or the construction of alternative apparatus, that work, instead of being executed by Esso, must be executed by the undertaker without unnecessary delay under the superintendence, if required, and to the reasonable satisfaction of Esso.

(7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 3000 millimetres of the apparatus without Esso’s consent unless that apparatus is redundant and disconnected from Esso’s remaining system and is more than 3000 millimetres from any live apparatus.

Back to top