C1PART 3Changes before or during construction

Annotations:

Change control applications: validity and time limitI122

1

Where the regulator receives a change control application which is valid the regulator must—

a

notify the applicant to that effect, and

b

determine it within 6 weeks beginning with the date the application is received by the regulator or within such longer period as at any time the regulator and the applicant agree in writing.

2

Where the regulator receives a change control application which is not valid the regulator must notify the applicant to that effect giving reasons (and where the applicant is not the client, also give a copy of the notification to the client).

3

A change control application is valid if it complies with regulation 21 (change control applications).