C1PART 3Changes before or during construction
Annotations:
Modifications etc. (not altering text)
Change control applications: validity and time limitI122
1
Where the regulator receives a change control application which is valid the regulator must—
a
notify the applicant to that effect, and
b
determine it within 6 weeks beginning with the date the application is received by the regulator or within such longer period as at any time the regulator and the applicant agree in writing.
2
Where the regulator receives a change control application which is not valid the regulator must notify the applicant to that effect giving reasons (and where the applicant is not the client, also give a copy of the notification to the client).
3
A change control application is valid if it complies with regulation 21 (change control applications).
Pts. 2-6 excluded (temp.) (6.4.2024) by The Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (S.I. 2024/110), regs. 1(3), 46(2)(c)