The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023

Change control applications: validity and time limitE+W

This section has no associated Explanatory Memorandum

22.—(1) Where the regulator receives a change control application which is valid the regulator must—

(a)notify the applicant to that effect, and

(b)determine it within 6 weeks beginning with the date the application is received by the regulator or within such longer period as at any time the regulator and the applicant agree in writing.

(2) Where the regulator receives a change control application which is not valid the regulator must notify the applicant to that effect giving reasons (and where the applicant is not the client, also give a copy of the notification to the client).

(3) A change control application is valid if it complies with regulation 21 (change control applications).

Commencement Information

I1Reg. 22 in force at 1.10.2023, see reg. 1(1)